Disbursement of public investment capital nationwide reached over 47% of the plan assigned by the Prime Minister.

Việt NamViệt Nam30/09/2024



The Ministry of Finance said that by the end of the third quarter, it is expected that public investment capital disbursement nationwide will reach nearly VND 320,567 billion, reaching 42.96% of the plan, reaching 47.29% of the plan assigned by the Prime Minister.

Ảnh minh họa.

The Ministry of Finance said that by the end of the third quarter, the disbursement value of public investment capital nationwide is expected to be nearly VND 320,567 billion, reaching 42.96% of the plan, reaching 47.29% of the plan assigned by the Prime Minister, lower than the same period in 2023 (reaching 47.75% of the plan and reaching 51.38% of the plan assigned by the Prime Minister). However, according to the Ministry of Finance, the disbursement rate of 9 key national transport projects is higher than the national average.

Accordingly, 9 national key projects in the transport sector are the North-South Eastern Expressway in the 2017-2020 period; the North-South Eastern Expressway in the 2021-2025 period; the Khanh Hoa-Buon Ma Thuot Expressway, phase 1; the Bien Hoa-Vung Tau Expressway, phase 1; the Chau Doc-Can Tho-Soc Trang Expressway, phase 1; the Hanoi Ring Road 4 project; the Ho Chi Minh City Ring Road 3 project; the Ho Chi Minh Road project; the Long Thanh airport compensation and resettlement support project are allocated public investment capital of VND 101,340.21 billion.

By the end of August 2024, the total disbursed capital for these 9 projects was VND 42,198.74 billion, reaching 41.6% of the plan. Compared to the country's general disbursement rate in the past 8 months of 36.7%, the disbursement rate of these 9 projects in the past 8 months is 4.9% higher.

According to the Ministry of Finance, according to the report of the Ministry of Transport, during the implementation process, these projects also encountered some difficulties and obstacles such as in site clearance, relocation of technical infrastructure in some localities of Binh Dinh, Dong Nai, Khanh Hoa, Tuyen Quang, Da Nang, Hung Yen, Kien Giang, Binh Duong, Lang Son, there is still a large volume that has not been completed according to the required schedule; the provinces of Tien Giang, Ben Tre, Vinh Long have implemented procedures for granting mines to contractors that have not met the schedule as directed by the Prime Minister (to be completed before August 30, 2024), affecting the construction progress of the projects; the implementation of investment procedures in some projects is still slow (Ring Road 4, Tuyen Quang - Ha Giang, Dong Dang - Tra Linh, Ben Luc - Long Thanh).

To achieve the Government's target of disbursing at least 95% of the assigned capital plan, the Ministry of Finance is requesting ministries, branches and localities to carry out tasks according to Decision No. 1006/QD-TTg dated September 19, 2024 of the Prime Minister on establishing working groups to inspect, urge, remove difficulties and obstacles, and promote annual disbursement of public investment capital at the units and localities under their management.

The Ministry of Finance recommends that ministries, branches and localities learn from experience in organizing and implementing projects, especially for large-scale projects with complex technical requirements, spread across many localities, urgent construction time, difficult terrain and weather conditions, and shortage of raw materials.

According to the Ministry of Finance, for these projects, ministries, branches and localities need to strengthen inspection and supervision, clearly assign responsibilities, and closely coordinate between levels and branches to ensure scientific and effective work.


According to PV/VTV

Source: https://doanhnghiepvn.vn/kinh-te/giai-ngan-von-dau-tu-cong-ca-nuoc-dat-tren-47-ke-hoach-thu-tuong-chinh-phu-giao/20240930083235832


Comment (0)

No data
No data

Event Calendar

Same tag

Same category

Same author

No videos available