Da Nang requires measures to deal with incompetent construction contractors

Báo Đầu tưBáo Đầu tư01/12/2024

To promote the disbursement of public investment capital plans, Da Nang requires capacity assessment, handling of contractors with poor capacity; reviewing units that do not fulfill their commitments on disbursing public investment capital plans.


Da Nang requires measures to deal with incompetent construction contractors

To promote the disbursement of public investment capital plans, Da Nang requires capacity assessment, handling of contractors with poor capacity; reviewing units that do not fulfill their commitments on disbursing public investment capital plans.

Chairman of Da Nang City, Mr. Le Trung Chinh, has just signed a document requesting to accelerate the disbursement of the 2024 Public Investment Capital Plan.

According to the People's Committee of Da Nang City, the disbursement of the public investment capital plan in 2024 has achieved some results. However, the implementation results so far have not met the set requirements.

In addition to objective reasons, the disbursement progress of the 2024 public investment capital plan is slow due to many subjective reasons under the responsibility of departments, branches, localities and investors.

To complete the disbursement of public investment capital in 2024, reaching 95% of the plan assigned by the Central Government, Da Nang City requires tightening discipline and order associated with the sense of responsibility of the unit's head in the process of handling documents and coordinating project implementation.

Da Nang City noted that the delay in coordinating the processing of documents and giving opinions from departments and branches is one of the main subjective reasons limiting the progress of disbursement of public investment capital.

The Chairman of Da Nang City requested to accelerate the 2024 public investment disbursement plan.

The Chairman of Da Nang City requested that heads of units take personal responsibility before the City People's Committee for the results of their units' work.

Require units, localities and project investors to actively review and shorten the time to carry out procedures related to appraisal and approval of design documents, construction drawings, project estimates, approval of investment projects, technical economic reports, approval of compensation and clearance procedures... to avoid cases of returning documents multiple times.

In addition, assess the disbursement capacity of each project, summarize the additional capital needs of the projects, propose plans for the City to approve the adjustment of the capital plan from slow-disbursement projects to good-disbursement projects...

The Chairman of Da Nang City also assigned the Department of Construction to preside over the review and assessment of capacity, and take appropriate measures to rectify and handle contractors and construction units with poor capacity, affecting the disbursement of public investment capital.

The Department of Home Affairs is responsible for evaluating, requesting units to review, and clarifying the responsibilities of each agency, locality, unit, and individual involved in failing to fulfill the committed targets and tasks regarding the disbursement of the 2024 public investment capital plan...

The total public investment capital plan for Da Nang in 2024 assigned by the Prime Minister is more than 7,291 billion VND. The capital plan assigned by the City People's Council is 8,881 billion VND, higher than the Central Plan assigned by 1,589 billion VND. Of which, the construction capital is 7,587 billion VND and the compensation capital is 1,294 billion VND.

As of October 17, the disbursement of the public investment capital plan according to the assigned budget for 2024 in Da Nang City reached VND 3,845 billion, reaching 43.3% of the plan assigned by the City, reaching 52.7% of the capital plan assigned by the Prime Minister. Of which, the disbursed central budget capital reached VND 787,789 billion, reaching 75.7% of the assigned plan.

It is estimated that by October 31, Da Nang City has disbursed 4,380 billion VND, equal to 60% of the capital plan assigned by the Prime Minister.



Source: https://baodautu.vn/da-nang-yeu-cau-co-bien-phap-xu-ly-nha-thau-thi-cong-kem-nang-luc-d231191.html

Comment (0)

No data
No data

Same tag

Same category

Helicopter squadron carrying the national flag flies over the Independence Palace
Concert Brother Overcomes a Thousand Difficulties: 'Breaking Through the Roof, Flying to the Ceiling, and Breaking Through the Heavens and Earth'
Artists are busy practicing for the concert "The Brother Overcame a Thousand Thorns"
Ha Giang Community Tourism: When endogenous culture acts as an economic "lever"

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product