Vietnam.vn - Nền tảng quảng bá Việt Nam

Hanoi requires completion of Ring Road 4 parallel road in October

Báo Giao thôngBáo Giao thông19/03/2025

The Chairman of the Hanoi People's Committee has just requested the completion of Component Project 2.1 to build parallel roads (urban roads) of the Ring Road 4 - Capital Region Construction Investment Project in Hanoi in October 2025.


The Office of the Hanoi People's Committee issued Notice No. 131 on the conclusion of the Chairman of the Hanoi People's Committee Tran Sy Thanh on the progress of the Investment Project to build Ring Road 4 - Capital Region.

Hà Nội yêu cầu hoàn thành đường song hành Vành đai 4 trong tháng 10- Ảnh 1.

Parallel road of Ring Road 4 through Me Linh.

Accordingly, the city leaders requested the People's Committees of districts to continue to focus on implementing and thoroughly resolving the remaining land area to be recovered, to be completed before April 15, 2025.

Notably, regarding the implementation of component projects, for Component Project 2.1 (parallel road, urban road), the City Traffic Construction Investment Project Management Board urged contractors to complete it in October 2025.

For Component Project 3 (expressway construction investment under the public-private partnership method), the City Traffic Construction Investment Project Management Board urgently prepares relevant documents so that after selecting an investor, it can immediately handle necessary procedures, ensuring the construction progress on May 19, 2025.

Previously, the Hanoi City Traffic Construction Investment Project Management Board said that up to now, 3 provinces and cities (Hanoi, Bac Ninh, Hung Yen) have approved plans and reclaimed more than 1,300 hectares of land, reaching 97.73%, and relocated nearly 16,600 graves, reaching 99.86%.

However, there are still many interruptions and gaps along the route. There are 18 sections with a length of about 4.38km that have not been handed over.

Regarding the progress of construction component projects, in the Hanoi section, after 20 months since the commencement date, 4 construction packages of Component Project 2.1 for parallel road construction (urban road) have been simultaneously implemented by contractors with 32 construction points (23 road points, 9 bridge points).

The volume of sand roadbed construction reached about 85.01%; soil roadbed construction reached about 62.27%; crushed stone mixture reached about 35.04%.

In Me Linh, Dan Phuong and Hoai Duc districts, the contractor has constructed about 30km of asphalt concrete.

Mr. To Ngoc Van - Director of the Hanoi Traffic Construction Investment Project Management Board affirmed that, based on updating and synthesizing data on the increase and decrease in total investment of component projects, the total investment of the Ring Road 4 Construction Investment Project - Hanoi Capital Region is expected to be adjusted down by about 2,570 billion VND compared to the preliminary total investment.



Source: https://www.baogiaothong.vn/ha-noi-yeu-cau-hoan-thanh-duong-song-hanh-vanh-dai-4-trong-thang-10-192250319073519486.htm

Comment (0)

No data
No data

Same tag

Same category

Tombs in Hue
Discover the picturesque Mui Treo in Quang Tri
Close-up of Quy Nhon port, a major commercial port in the Central Highlands
Increasing Hanoi's attractiveness from flower tourism spots

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product