BPO - After a period of urgent construction, on the afternoon of November 27, Binh Phuoc Power Company organized the energization and operation of the Loc Ninh 110kV 2x63 MVA Station project in Loc Hung commune, Loc Ninh district. Attending the energization ceremony were leaders of the Southern Power Corporation and Binh Phuoc Power Company.
Leaders of Southern Power Corporation inspect the energization process at Loc Ninh 110kV Transformer Station
The 110kV Loc Ninh 2x63 MVA transformer station project is invested by the Southern Power Corporation with a total capital of over 71 billion VND. In particular, the capacity of 2 transformers is increased from 2x25 MVA to 2x63 MVA, which will help increase the reliability of N-1, connect the 22kV grid of the 110kV Loc Ninh station with the 110kV Binh Long and Bu Dop transformer stations, and enhance the ability to supply electricity to loads in Loc Ninh district and localities bordering Cambodia.
Technical staff of Loc Ninh 110 kV Transformer Station, Binh Phuoc Electricity Company, perform the energizing and operating process of transformer T1.
Successfully energized transformer T1
Faced with the urgent need for electricity for daily life and production in Binh Phuoc province, the Southern Power Corporation has approved the investment policy and directed construction units to urgently speed up the progress, complete and energize 4 transformer station projects in localities in November 2024.
Source: https://baobinhphuoc.com.vn/news/4/165852/dong-dien-tram-110kv-loc-ninh-2x63-mva