According to Nhan Dan Newspaper reporters on the morning of March 21, in many areas on the To Lich River, construction units are urgently dredging the riverbed and building dams...
![]() |
Workers of Hanoi Drainage Company are dredging and clearing the entire To Lich River bed. |
![]() |
Combined with specialized machinery to ensure the dredging process is on schedule. |
![]() |
Road along both banks of To Lich River. |
![]() |
The required progress is that in the third quarter of 2025, dredging must be completed so that the units implementing the project of taking water from the Red River into the To Lich River can start building infrastructure items such as pumping stations, ditches, channels, especially dams to retain and regulate water. The dams to retain water have been initially identified at the following locations: Cot Bridge (Yen Hoa, Cau Giay), Dau Bridge (Linh Dam, Hoang Mai), Quang Bridge (Thanh Liet, Thanh Tri). |
![]() |
At Quang bridge area (Thanh Liet, Thanh Tri), construction units have cordoned off and drained the water to build a dam. |
![]() |
The To Lich River here has been narrowed to about 2 meters to ensure drainage. |
![]() |
Workers are working busily on the construction site. |
![]() |
Equipment and machinery are ready to construct the first dam on the To Lich River . |
![]() |
The To Lich River dredging project, despite many difficulties, has created positive changes in improving the environment, protecting the ecosystem and enhancing the quality of life for the people of the capital. |