Workers and machinery were mobilized to construct Nhon Trach Bridge, part of component project 1A of Ho Chi Minh City Ring Road 3, with the goal of completing the entire project by April 30.
The large construction site of Nhon Trach bridge connecting Ho Chi Minh City and Dong Nai worth 1,600 billion VND before the closing day
Thursday, March 6, 2025 09:24 AM (GMT+7)
Workers and machinery were mobilized to construct Nhon Trach Bridge, part of component project 1A of Ho Chi Minh City Ring Road 3, with the goal of completing the entire project by April 30.
Nhon Trach Bridge belongs to Ring Road 3 connecting Ho Chi Minh City and Nhon Trach District (Dong Nai Province) with a total length of 8.22 km, of which 6.3 km passes through Dong Nai Province and 1.92 km passes through Ho Chi Minh City.
Nhon Trach Bridge has a total investment cost of about 1,600 billion VND, is package CW1 - one of two construction packages in component project 1A, Tan Van - Nhon Trach section of Ring Road 3 project, Ho Chi Minh City.
According to Dan Viet reporters, hundreds of workers and machinery were mobilized to carry out construction at the Nhon Trach bridge construction site.
Nhon Trach Bridge will start construction in September 2022, with phase 1 consisting of 4 motor lanes and 2 mixed lanes. The entire project is expected to be completed by April 30.
According to the My Thuan Project Management Board, after the closing, the Nhon Trach bridge project will enter the finishing stage with important steps such as asphalt paving, external cable tensioning to strengthen the structure, and construction of the railing system to ensure safety.
Nhon Trach Bridge is designed with 39 piers and 2 abutments. According to the design, the bridge is 20.2 m-26 m wide, with a design speed of 80 km/h. After completion, the Nhon Trach Bridge project will shorten the travel time between Ho Chi Minh City and Dong Nai.
In the CW2 package (construction of the 5.6km long approach road at both ends of the bridge) with a value of 1,071 billion VND, the progress has reached over 75%. According to the contract, this package is due to expire on September 29, but is ahead of schedule and is expected to be basically completed by April 30.
Recently, My Thuan Project Management Board has launched and organized a 60-day competition to determine the technical traffic opening of component project 1A, Tan Van - Nhon Trach section, phase 1, of Ho Chi Minh City Ring Road 3.
Component project 1A of Ring Road 3, Ho Chi Minh City, after completion and put into operation, will increase connectivity between Ho Chi Minh City and neighboring provinces, connect satellite cities, promote economic and social development for the key economic region of the Southeast.
Component project 1A has a total investment of 6,900 billion VND, of which the ODA capital from Korea is nearly 4,176 billion VND. The remaining amount is the counterpart capital of the Vietnamese Government with the central capital of about 529 billion VND, the rest is the budget of 2 localities, Dong Nai and Ho Chi Minh City.
The project plays an important role in shortening the journey from Ho Chi Minh City to Dong Nai, to Long Thanh International Airport and neighboring provinces. After putting the entire project into operation and connecting to the intersection with component project 1, expected on June 30, 2025, it will help reduce the load on the Ho Chi Minh City - Long Thanh - Dau Giay expressway and contribute to remote traffic flow, reducing congestion on expressways as well as the inner-city road system of Ho Chi Minh City.