(NLDO) - On the afternoon of March 12, Deputy Prime Minister Le Thanh Long inspected the site of two expressway projects in Khanh Hoa to ensure the set progress.
On the afternoon of March 12, Deputy Prime Minister Le Thanh Long led a working delegation to inspect the construction progress of two expressway projects: Van Phong - Nha Trang and Khanh Hoa - Buon Ma Thuot (component project 1).
The Van Phong – Nha Trang component project, 83.35 km long (located entirely in Khanh Hoa province), is invested by Project Management Board 7 with a total investment of VND 11,808 billion. The project is carried out by the Khanh Hoa Provincial People's Committee for site clearance.
Van Phong - Nha Trang expressway is under construction.
The project started construction in early 2023 and is expected to be completed according to the contract in December this year. To date, the project has basically completed site clearance and relocation of technical infrastructure works serving the project.
Regarding the problems, Khanh Hoa Provincial People's Committee has directed relevant units to urgently resolve and hand over the site for the project such as: 3 additional residential roads, rest stop in Ninh Hoa town...
Deputy Prime Minister Le Thanh Long (in blue shirt, third from right) inspects the progress of expressway projects in Khanh Hoa.
The Khanh Hoa - Buon Ma Thuot Expressway Project (Component 1) through Khanh Hoa province is 31.5 km long and was decided to be invested by the Khanh Hoa Provincial People's Committee with a total capital of VND 5,333 billion. The project started in June 2023. Khanh Hoa province strives to complete the first 20 km of the route by 2025 according to the Prime Minister's direction, the remaining section is expected to be completed in 2026.
This project has a clearance area of about 228.17 hectares with a total of 1,033 affected cases, requiring resettlement of about 101 households.
Currently, the project is stuck with 16 sections, including 12 sections through areas with houses on land that must be resettled and 4 sections through areas that do not have resettlement.
Deputy Prime Minister Le Thanh Long requested the People's Committee of Khanh Hoa province to make efforts to resolve difficulties and meet progress.
After the field inspection, Deputy Prime Minister Le Thanh Long praised the efforts of the locality, investors and contractors in site clearance and construction, especially the Van Phong - Nha Trang Expressway Project.
However, at the Khanh Hoa - Buon Ma Thuot Expressway Project, there are still many locations where the land has not been handed over, the construction output is still low, not meeting the set plan.
The Deputy Prime Minister requested that localities, investors and contractors must be more determined and make more efforts to meet the schedule of completing projects in the list of 3,000 km of expressways by 2025.