Assessment of public investment disbursement situation in the first quarter of 2025 - Lang Son Newspaper

Việt NamViệt Nam21/03/2025


- On March 21, Comrade Luong Trong Quynh, Vice Chairman of the Provincial People's Committee chaired a meeting to evaluate the implementation and disbursement of the first quarter public investment plan and deploy tasks for the second quarter.

Comrade Luong Trong Quynh, Vice Chairman of the Provincial People's Committee spoke at the meeting.
Comrade Luong Trong Quynh, Vice Chairman of the Provincial People's Committee spoke at the meeting.

According to the report at the meeting, in 2025, the province's public investment capital assigned by the Prime Minister is 5,710,221 billion VND and has implemented detailed allocation of 100% of the plan.

As of March 14, 2025, investors have disbursed VND 332.4 billion, reaching 5.8%, 1.1% lower than the national average (6.9%) and 6.9% lower than the same period in 2024.

Leaders of Loc Binh District People's Committee report on the progress of disbursement of capital managed by the district
Leaders of Loc Binh District People's Committee report on the progress of disbursement of capital managed by the district

Evaluating disbursement results by investor group, the disbursement rate of capital managed by the provincial level was 197/5,492.9 billion VND, reaching 3.6% of the plan. Of which, 19/26 investors had a disbursement rate below the average of the province.

Regarding capital managed by the district level, investors have disbursed 135.3 billion VND, reaching 11.4% of the plan. Of which, 3/11 districts disbursed below the average level of the province: Binh Gia (0.7%); Trang Dinh (2.3%), Loc Binh (1.4%).

Overall, by mid-March 2025, investors disbursed public investment capital plans slower than planned and required by the Provincial People's Committee.

Leaders of the Provincial Construction Investment Project Management Board report on the implementation status of projects.
Leaders of the Provincial Construction Investment Project Management Board report on the implementation status of projects.

At the meeting, representatives of investors explained and clarified a number of reasons for the low disbursement results such as: site clearance work for some projects is still slow; construction progress at some projects has not met the plan; some projects are still slow to complete settlement documents...

Concluding the meeting, the Vice Chairman of the Provincial People's Committee requested that investors focus on directing and operating to achieve the disbursement target according to the general plan of the whole country, by the end of March 31, 2025, it must reach 12%.

Regarding the tasks of the second quarter, the Vice Chairman of the Provincial People's Committee requested that investors develop detailed disbursement plans, review the volume of each project, and urge construction by month to ensure the disbursement progress of investors as committed to the Provincial People's Committee at the meeting.

Regarding the Huu Nghi - Chi Lang border gate expressway project, which is a project with a large amount of capital, the Vice Chairman of the Provincial People's Committee requested the Provincial Construction Investment Project Management Board to focus on directing, urging and regularly checking the contractor's construction progress to report to the Provincial People's Committee to monitor the implementation situation every week.

At the same time, the Provincial Investment and Construction Project Management Board and the Department of Construction urgently completed investment procedures, appraised and approved the project to upgrade and expand the water supply system of Loc Binh town, Loc Binh district; the Department of Agriculture and Environment urgently advised the Provincial People's Committee to auction land use rights and speed up the collection of land use fees at urban area projects.

At the same time, the People's Committees of districts, cities and provincial-level investors need to resolutely and seriously implement the direction of the Provincial People's Committee in Decision No. 245/QD-UBND dated January 23, 2025 on the main tasks and solutions to direct and implement the Socio-Economic Development Plan and State Budget Estimates for 2025, Directive No. 05/CT-UBND dated March 12, 2025 on accelerating the progress of implementation and disbursement of public investment capital and capital for implementing national target programs in 2025. In addition, the People's Committees of districts need to focus on handling difficulties and bottlenecks in site clearance to promptly hand over clean sites, contributing to accelerating the construction progress of projects, especially expressways.



Source: https://baolangson.vn/hop-danh-gia-tinh-hinh-giai-ngan-von-dau-tu-cong-quy-i-nam-2025-5041612.html

Comment (0)

No data
No data

Same tag

Same category

Concert Brother Overcomes a Thousand Difficulties: 'Breaking Through the Roof, Flying to the Ceiling, and Breaking Through the Heavens and Earth'
Artists are busy practicing for the concert "The Brother Overcame a Thousand Thorns"
Ha Giang Community Tourism: When endogenous culture acts as an economic "lever"
Southeast Asian fans react when Vietnam team defeats Cambodia

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product