Hong Linh Town Square gradually takes shape, promising to reach the finish line soon

Việt NamViệt Nam23/09/2023

The Hong Linh Town Square project (Ha Tinh) has completed 70% of the work. Contractors are rushing to speed up progress, striving to complete phase 1 ahead of schedule.

VIDEO: Bustling at the construction site of Hong Linh Town Square, phase 1

Hong Linh Town Square gradually takes shape, promising to reach the finish line soon

The Hong Linh Town Square project, invested by the Town People's Committee, is built in Bac Hong Ward. Phase 1 of the project is being built on an area of ​​over 3.4 hectares with a total investment of 67 billion VND.

Hong Linh Town Square gradually takes shape, promising to reach the finish line soon

Started in January 2023, the project is identified as an important project contributing to the completion of the infrastructure system, completing the criteria for building the town to reach the level of a type III urban area. After 9 months of construction, the project has achieved 70% of the total workload. The project items have been completed such as: leveling the ground with a total area of ​​over 34 hectares...

Hong Linh Town Square gradually takes shape, promising to reach the finish line soon

...green system...

Hong Linh Town Square gradually takes shape, promising to reach the finish line soon

... power supply and lighting system for the square.

Hong Linh Town Square gradually takes shape, promising to reach the finish line soon

These days, taking advantage of the sunny weather, the construction unit is focusing on completing the traffic system of 4 routes with a total length of 999m...

Hong Linh Town Square gradually takes shape, promising to reach the finish line soon

... paving the square area.

Hong Linh Town Square gradually takes shape, promising to reach the finish line soon

Contractor for construction of sports complex and parking lot with an area of ​​nearly 4,000m2

Hong Linh Town Square gradually takes shape, promising to reach the finish line soon

The Square area with logo and stage is being focused on by the contractor to ensure progress, completing nearly 70% of the volume.

Hong Linh Town Square gradually takes shape, promising to reach the finish line soon

Mr. Le Van Thanh - Technical Officer of Dai Phong Construction and Trading Consulting Co., Ltd. - one of the three contractors undertaking the construction of the project said: "The unit is focusing on completing items such as traffic system, logo symbol, stage, internal yard and parking lot. Striving to complete the project by December 30, 2023, 8 months ahead of schedule".

Hong Linh Town Square gradually takes shape, promising to reach the finish line soon

Mr. Nguyen Cong Thien - Director of Hong Linh Town Construction Investment Project Management Board said: "The unit is continuing to direct contractors to implement the remaining items to complete the project. With the current construction progress, the goal of completing phase 1 of Hong Linh Town Square and handing over 8 months ahead of schedule is completely feasible."

Nam Giang


Source

Comment (0)

No data
No data

Same tag

Same category

Spreading national cultural values ​​through musical works
Lotus color of Hue
Hoa Minzy reveals messages with Xuan Hinh, tells behind-the-scenes story of 'Bac Bling' causing global fever
Phu Quoc - tropical paradise

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product