With the provincial budget, in 2023, Quan Hoa High School will invest in building a 3-storey headquarters building with 15 functional rooms; a multi-purpose building; a fire prevention and fighting system; auxiliary items... with a total investment of nearly 14.98 billion VND. The Quan Hoa District Construction Investment Project Management Board has assigned technical staff to regularly monitor the site and coordinate with the contractor to resolve difficulties and problems arising during the construction process.
The project to arrange and stabilize the population of Say village, Trung Thanh commune is being accelerated by the contractor.
With the close direction of Quan Hoa district and the District Construction Investment Project Management Board, the construction of the school's headquarters and multi-purpose building... of Quan Hoa High School was accelerated and completed on schedule, ensuring quality. Currently, the project has been put into use, making an important contribution to improving the school's education quality.
In 2024, Quan Hoa district will implement 147 projects (including 97 transitional projects, 50 newly started projects) with a total investment of more than 187 billion VND. Some of the key projects include: Road from Tang village to Say village, Trung Thanh commune; arranging and stabilizing the population of Say village households, Trung Thanh commune; upgrading and repairing the road from Bo village, Trung Son commune; road from Hoi Xuan town...
In order to complete the projects on schedule and ensure quality, the People's Committee of Quan Hoa district has established a Land Clearance Council to coordinate with functional units to resolve difficulties and obstacles in the process of compensation and land clearance; resolutely handle households that do not comply with the land recovery decision despite having sufficient legal grounds. At the same time, the district has directed specialized departments and offices to effectively implement administrative procedure reform, creating favorable conditions for projects to be implemented according to plan. Every month, the People's Committee of the district organizes meetings with specialized agencies and localities with projects to assess the progress of each project and promptly handle problems and arising issues. Currently, many projects in Quan Hoa have completed 80% or more of the construction volume. Typical projects include: Phu Thanh Secondary School for Ethnic Minorities; Hoi Xuan Town Kindergarten; Na Pa Cha Dam in Yen Village, Hien Chung Commune; Thanh Son Kindergarten, etc.
In addition to the achieved results, many works and projects in Quan Hoa district are also behind schedule compared to the plan, such as: Traffic road from Ba village, Phu Xuan commune to the hard bridge of Phu Thanh commune; traffic road from Nga village, Nam Tien commune to Khuong Lang village, Nam Dong commune; police headquarters of Phu Son and Trung Thanh communes...
In fact, it is known that the reason why many projects and works in Quan Hoa district are behind schedule is mainly due to difficulties and obstacles in site clearance. According to information from the People's Committee of Quan Hoa district, in 2024, the district has 11 projects that need site clearance with a total area of 19.62 hectares. However, by April 15, 2024, the district has only cleared 7.4% of the registered area. The delay in site clearance not only affects the progress of construction projects and works but also affects the disbursement of public investment capital in 2024.
Ms. Ha Thi Nga, Vice Chairman of Quan Hoa District People's Committee, said: To speed up the construction of works and projects, Quan Hoa district continues to promote propaganda work, creating consensus among the people in site clearance work. Directing the District Construction Investment Project Management Board to assign staff to supervise and urge contractors to arrange vehicles, machinery, equipment, and human resources to organize overtime, ensuring progress and quality according to the set plan. Conducting the preparation of documents, price vouchers for payment of completed volume and timely disbursement for works eligible for capital payment to contribute to completing the task of disbursing public investment capital, putting works into use soon, promoting the efficiency of investment capital, promoting the socio-economic development of Quan Hoa district.
Article and photos: Xuan Cuong