Nearly 9,000 billion VND invested in PPP for Dau Giay Expressway

Báo Giao thôngBáo Giao thông02/08/2024


The Ministry of Transport has just issued a decision approving the investment project to build the Dau Giay - Tan Phu expressway (phase 1) under the PPP method.

Gần 9.000 tỷ đồng đầu tư PPP cao tốc Dầu Giây - Tân Phú- Ảnh 1.

The Dau Giay - Tan Phu Expressway project is expected to be basically completed in 2026 and put into operation from 2027 (Illustration photo).

According to the approved plan, the project has a total length of more than 60km.

Starting point Km0+000, at the intersection with National Highway 1, connecting with Ho Chi Minh City - Long Thanh - Dau Giay Expressway, in Dau Giay town, Thong Nhat district, Dong Nai province.

The end point is at Km60+243.83 (end of the intersection with National Highway 20), connecting with the Tan Phu (Dong Nai) - Bao Loc (Lam Dong) Expressway Construction Project, located in Phu Trung commune, Tan Phu district, Dong Nai province.

In phase 1, the project is invested with geometric elements (plan, longitudinal profile) meeting the standards of a class 100 highway, with a scale of 4 lanes and a roadbed width of 17m.

At locations where weak ground is treated, roadbeds are excavated, raised, within the scope of interchanges, emergency stops, and highway bridges, the cross-section is designed according to the scale of the completed phase with a roadbed width of 24.75m.

Completed phase, completed phase, the expressway is invested in the scale of a class 100 expressway, with a scale of 4 lanes, a roadbed width of 24.75m, and a design speed of 100 km/h.

The site clearance work is carried out in a phased manner with 4 lanes completed and a roadbed width of 24.75m. The total land area occupied is approximately 378ha.

With the above plan, the total investment of the project is more than 8,981 billion VND. Of which, site clearance cost is more than 1,454 billion VND; construction cost is more than 5,562 billion VND; equipment cost is more than 200 billion VND; project management cost is more than 32 billion VND; investment consulting cost is more than 157 billion VND; other costs are nearly 590 billion VND; contingency cost is more than 983 billion VND.

Regarding capital structure, the capital mobilized by investors is about 7,681 billion VND. The planned capital allocation in 2025 is about 30%, in 2026 about 40%, in 2027 about 30%.

The state capital participating in the project is about 1,300 billion VND under the medium-term public investment plan of the state budget for the period 2021 - 2025 approved by the Prime Minister. The expected capital allocation plan in 2025 is about 62%, in 2026 about 38%.

The project's payback period is calculated to be 18 years, 2 months and 11 days.

The Dau Giay - Tan Phu project is an important piece on the Dau Giay - Lien Khuong expressway. The project is invested to meet the transportation demand, reduce the load and ensure traffic safety on National Highway 20, contributing to the synchronous exploitation of high-capacity, high-speed expressways on the Ho Chi Minh City - Dau Giay - Lien Khuong transport corridor, promoting the socio-economic development of Dong Nai province in particular and the Southeast region in general.

The project will also create a driving force for linkage, promote cooperation and development between the Southeast region and the Mekong Delta, the Central Highlands and the South Central Coast; increase the competitiveness of the economy in the context of deep integration.



Source: https://www.baogiaothong.vn/gan-9000-ty-dong-dau-tu-ppp-cao-toc-dau-giay-tan-phu-192240802121209987.htm