The Hanoi People's Committee has just issued an official dispatch on implementing the Prime Minister's direction at the 16th meeting of the State Steering Committee for important national projects and works, key to the transport sector.

Specifically, in implementing the investment project to build Ring Road 4 - Capital Region, the City People's Committee requested the districts: Ha Dong, Soc Son, Me Linh, Dan Phuong, Hoai Duc, Thanh Oai, Thuong Tin to implement the Prime Minister's direction to complete the site clearance work on time.

The People's Committee assigned the Department of Finance to urgently advise and propose a report to the city to transfer the 2024 planned capital source allocated to the investment project to ensure funding sources to pay for the implemented volume of the investment project.

bridge 4 258.jpeg
Perspective of Ring Road 4. Photo: Document

The Traffic Construction Investment Project Management Board is required to urgently prepare relevant documents so that after selecting an investor, it can immediately handle the necessary procedures, ensuring the construction progress on May 19, 2025.

For railway construction investment projects (North-South high-speed railway, Lao Cai - Hanoi - Hai Phong railway), the City People's Committee assigned the Departments of Finance, Agriculture and Environment, Construction and the districts of Me Linh, Dong Anh, Gia Lam, Thanh Tri, Thuong Tin, Phu Xuyen to coordinate with the Railway Management Board - Ministry of Construction to immediately deploy documents, processes, procedures for site clearance, determine needs, resettlement locations, approve resettlement projects to ensure project progress.

For the urban railway construction investment project, route 2.1 Nam Thang Long - Tran Hung Dao, the city assigned the Department of Finance to preside over and coordinate with the Urban Railway Management Board to advise, propose, and report on the procedures for advancing the city's budget during the time of completing the negotiation procedures and signing the ODA loan agreement.

The Department of Agriculture and Environment is assigned to preside over and coordinate with the Urban Railway Management Board and the People's Committee of Bac Tu Liem District to proactively coordinate with relevant units of the Ministry of National Defense to urgently relocate Battalion 10 - Artillery Command to implement the project to ensure progress.

Ring Road 4 - the capital region has a total length of 112.8km, of which the section passing through Hanoi is 56.5km, Hung Yen 20.3km, Bac Ninh 21.2km.

The project includes 103.1km of Ring Road 4 and 9.7km of connecting route towards Noi Bai - Ha Long Expressway, with a total investment of about VND 85,813 billion, divided into 3 groups with 7 component projects.

Starting point at km3+695 on Noi Bai - Lao Cai highway (Thanh Xuan commune, Soc Son, Hanoi), ending point on Noi Bai - Ha Long highway (Que Vo district, Bac Ninh province).