Da Nang urges site clearance for Hoa Lien - Tuy Loan Expressway project
Inspecting the actual implementation of the Hoa Lien - Tuy Loan Expressway project, Secretary of the Da Nang City Party Committee, Mr. Nguyen Van Quang requested to actively speed up the site clearance progress.
On April 17, Secretary of the Da Nang City Party Committee, Mr. Nguyen Van Quang inspected the site clearance work of the Hoa Lien - Tuy Loan Expressway project.
The Hoa Lien - Tuy Loan Expressway Project has a total length of 11.5km, with about 1,166 records requiring land clearance, passing through the area of 3 communes of Hoa Lien, Hoa Son, Hoa Nhon (Hoa Vang district).
In recent times, Hoa Vang district has focused and made great efforts to carry out the project's site clearance. As of April 15, 1,068 records have been counted, reaching 92%; 752/1,166 records have been priced. In addition, 580/916 records of agricultural land and other land have been handed over; the handover has been completed with a length of 6.2km/11.5km...
![]() |
Secretary of the Da Nang City Party Committee, Mr. Nguyen Van Quang inspected the site clearance work of the Hoa Lien - Tuy Loan Expressway project. |
Regarding the work of relocating graves, there are about 2,908 graves along the route that need to be relocated, and so far 581 graves have been relocated.
Through the actual inspection of the Project, Secretary of the Da Nang City Party Committee, Mr. Nguyen Van Quang acknowledged the efforts of the Management Boards and Hoa Vang district in actively speeding up the site clearance progress.
According to the Secretary of the Da Nang City Party Committee, this is a national key project, so it is necessary to focus more on the project's construction. Mr. Nguyen Van Quang requested the Party Committee of the City People's Committee to direct the City People's Committee and departments to speed up the appraisal of environmental impact assessment reports, complete the construction documents of 2 resettlement areas, and serve the relocation of people.
![]() |
The Hoa Lien – Tuy Loan Expressway project is being implemented. |
The Secretary of the Da Nang City Party Committee also requested that any favorable locations must be implemented first and the site clearance, route clearance, and handover to the construction unit must be focused on. Wherever the site is available, construction must be carried out...
Source
Comment (0)