The project is invested by the Hanoi City Civil Construction Investment Project Management Board.
In terms of scale, the investment in new construction of construction items includes: 1 basement with an area of about 11,490m2; 2-storey ceremonial hall, total floor area of about 2,155m2; 6-storey administrative block, total floor area of about 7,025m2; 5-storey study block - toilet, total floor area of about 16,050m2, total floor area of the toilet is about 416m2; 5-storey library, total floor area of about 4,295m2; 2-storey meeting hall, total floor area of about 1,422m2; 14-storey dormitory - dining room, total floor area of about 18,740m2; 2-storey gym, total floor area of about 1,432m2.
Auxiliary technical items: with a construction floor area of about 1,025m2 including bridge corridors, garbage collection yard, guard house gate, 4 parking lots on the ground (total area of 4 parking lots is about 633m2)...
Synchronous investment in garden landscape items. Logo, signboard, school name designed in a synchronous manner in terms of light style, color and material. New investment in synchronous equipment for the building blocks.
Total land area is about 42,175.32m2 including: Land area within the planned road opening scope is about 1,682.32m2; Land area for project implementation is about 40,493m2.
The project has a total investment of 980 billion VND, from the city budget. Implementation period is from 2022 - 2026.
Source: https://kinhtedothi.vn/phe-duyet-du-an-xay-dung-truong-dao-tao-can-bo-le-hong-phong-tai-quan-ha-dong.html