The Project's objective is to gradually complete the expressways in the Road Network Planning for the period 2021 - 2030, with a vision to 2050, approved by the Prime Minister in Decision No. 1454/QD-TTg dated September 1, 2021. Connecting expressways from Thanh Hoa, Ninh Binh, Nam Dinh, Thai Binh provinces to Hai Phong and Quang Ninh cities; creating momentum for the development of provinces and cities in the Red River Delta and North Central regions; serving as a basis for attracting investors in many fields, especially urban, industrial, commercial and service development; promptly responding to natural disasters and climate change in the region; strengthening national defense and security.
Investing in the construction of the Ninh Binh - Hai Phong expressway, the section through Nam Dinh and Thai Binh provinces with a length of about 60.9 km; of which, 27.6 km is in Nam Dinh province, 33.3 km is in Thai Binh province. The starting point of the project is at Km19+300 at the head of the Day River overpass in Nam Dinh, in Nghia Thai commune, Nghia Hung district, Nam Dinh province. The end point is at about Km80+200 at the intersection between the new National Highway 37 and the coastal road, in Thuy Trinh commune, Thai Thuy district, Thai Binh province.
Investing in building the route according to expressway standards (TCVN 5729:2012), 04 complete lanes, roadbed width Bnền=24.75m, design speed 120km/h.
The Project implementation period is expected to be from 2023 to 2027. The total investment excluding interest is VND 18,927.63 billion. The total investment including interest is VND 19,784.55 billion.
The estimated demand for land, water surface, and other resources is about 522.63 hectares; of which, Nam Dinh province is 251.15 hectares; Thai Binh province is 271.48 hectares.
Thai Binh Provincial People's Committee is fully responsible for the information and data in the Project's Pre-Feasibility Study Report and the information reported on receiving and explaining opinions of relevant ministries and agencies, and appraisal opinions of the Interdisciplinary Appraisal Council; and posting notices inviting investors to survey their interest in the Project as prescribed in Article 25 of Decree No. 35/2021/ND-CP dated March 29, 2021.
Perform the responsibility as a competent authority; preside over and coordinate with the People's Committee of Nam Dinh province and relevant agencies and units to organize the preparation of the Project Feasibility Study Report, carry out the procedures for appraisal and approval of Project investment, organize the implementation of the Project in accordance with the approved planning and relevant legal regulations, ensure quality, progress, efficiency, and prevent negativity and waste that cause loss of State assets and capital.
Ensure balance, full and timely allocation of provincial budget capital to participate in the Project in accordance with legal regulations to implement the Project on schedule.
Organize compensation, support, resettlement and complete procedures for land allocation, land lease, and handover of premises within the scope of management to implement the Project in accordance with the provisions of the law on land and the law on investment under the public-private partnership method.
Nam Dinh Provincial People's Committee closely coordinates with Thai Binh Provincial People's Committee in the process of implementing the Project in accordance with legal regulations.
Ensure balance, full and timely allocation of provincial budget capital to participate in the Project in accordance with legal regulations to implement the Project on schedule.
Organize compensation, support, resettlement and complete procedures for land allocation, land lease, and handover of premises within the scope of management to implement the Project in accordance with the provisions of the law on land and the law on investment under the public-private partnership method.