On July 16, the People's Committee of Da Nang City reported on the implementation of major projects according to Resolution No. 25 of the City People's Council.
Regarding the railway station relocation project, the People's Committee of Da Nang City has directed the city's Department of Transport to work with the Ministry of Transport and relevant agencies to agree on a preliminary plan to arrange a freight station at Kim Lien and a passenger station at Trung Nghia.
Da Nang is implementing steps to build a tunnel through the airport.
At the same time, make plans and develop plans for site clearance and resettlement for Kim Lien station area and Trung Nghia area.
In the coming time, the People's Committee of Da Nang City will review the final report and send a written report to the Ministry of Transport on the proposed investment plan for the passenger and cargo terminals.
After consulting with the Ministry of Transport and relevant agencies and units, the People's Committee of Da Nang City assigned the Department of Transport to coordinate with relevant units to complete the dossier and submit it to the City People's Committee for submission to competent authorities according to regulations, expected in July 2024.
Next is the investment project to build a project across the Han River (Han River Tunnel). This project will connect the Dong Da - Tran Phu street area (Hai Chau district) to Van Don - Tran Hung Dao street (Son Tra district).
According to the report, the People's Committee of Da Nang City has directed the Department of Transport to propose capital allocation in 2024 to carry out investment preparation work.
Up to now, the Department of Transport has proactively worked with experts in the field to research options as well as review and update related zoning plans to ensure consistency. On that basis, a survey plan has been developed to serve the selection of a design consultant to prepare a project pre-feasibility study report.
"Currently, the Department of Transport is coordinating with relevant units to organize the appraisal and approval of the budget for the investment preparation task. It is expected that the selection of consultants to prepare the project's pre-feasibility study report will be completed within 3 months from the date of investment preparation capital allocation," the report stated.
The People's Committee of Da Nang City added that it is expected to complete and submit the project's pre-feasibility study report to competent authorities for appraisal in December 2024 and complete the feasibility study report in August 2025.
Another key transportation project is the tunnel project through Da Nang airport.
Up to now, the City People's Committee has directed the Department of Transport to proactively invite and work with experts to study the project's options and scale as well as review and coordinate updates to related zoning plans to ensure consistency. On that basis, develop tasks and survey plans to serve the selection of design consultants to prepare a project pre-feasibility study report.
Currently, the Department of Transport is coordinating with relevant units to organize the appraisal and approval of the budget for investment preparation tasks. It is expected that the selection of consultants to prepare the project's pre-feasibility study report will be completed within 3 months from the date of investment preparation capital allocation.
Da Nang City People's Committee said that it is expected to complete the selection of consultants to prepare a pre-feasibility study report after 3 months from the date of investment preparation capital allocation (expected in September 2024).
"It is expected to complete the project's pre-feasibility study report (final report) in the first quarter of 2025 and complete the feasibility study report in the third quarter of 2025," the report stated.