In 2025, the total capital allocated for infrastructure investment in Loc Son Industrial Park, Bao Loc and Phu Hoi Industrial Park, Duc Trong is nearly 14.5 billion VND.
By the end of the first quarter of 2025, at Phu Hoi Industrial Park, the centralized wastewater treatment plant and wastewater collection system (funding source in 2025 is nearly 12 billion VND) have completed about 87% of the volume. And 500 million VND for sidewalk and tree construction has proposed the project investment policy.
At Loc Son Industrial Park, they are organizing the preparation, appraisal of the budget and planning to select a contractor for the preparation phase of investment in upgrading the centralized wastewater treatment plant, with a total capital of 1 billion VND. The sidewalk and tree project alone, which is allocated 1 billion VND, has submitted a report proposing the investment policy for phase 1 - 2025.
Source: http://baolamdong.vn/kinh-te/202503/dau-tu-xay-dung-ha-tang-2-khu-cong-nghiep-7050177/