On August 27, according to a source from Giao Thong Newspaper, the Chairman of the People's Committee of Ca Mau province issued a document requesting to stop signing the contract for package 27 of Ca Mau General Hospital until the competent authority issues a document to resolve the petition in accordance with regulations.
The project to build the new 1,200-bed Ca Mau General Hospital has started leveling the ground and surrounding fences. (Photo taken in May 2024).
The project to invest in building Ca Mau General Hospital with a scale of 1,200 beds, invested by the Ca Mau Provincial Construction Project Management Board.
Previously, Thuan Phu Company Limited (Chau Thanh District, Tien Giang Province) and Corporation 36 - Joint Stock Company (Dong Da District, Hanoi City) both submitted petitions to review the results of contractor selection for package No. 27, because they believed that it did not ensure objectivity, transparency and compliance with the law in bidding.
Package No. 27 for construction of main building, static pile load testing, water supply and drainage is one of the main packages of the project. This package is worth more than 822 billion VND, invited for online bidding from April 6, 2024 and closed on May 22, 2024.
The Ca Mau Provincial General Hospital project is built on an area of 12.15 hectares in Ward 6, Ca Mau city, with implementation period from 2020-2025.
The project has a total investment of more than 3,300 billion VND, including: construction costs of more than 1,400 billion VND; costs of electromechanical equipment and technological equipment of more than 500 billion VND; costs of medical equipment of more than 854 billion VND...
Currently, the project has only partially completed site leveling, pile driving, concrete pouring, internal traffic routes, etc.
In 2024, the province will allocate more than 397 billion VND in capital, of which more than 208 billion VND will come from the provincial lottery, and the remaining 188 billion VND will come from the central budget.
As of July 31, the investor disbursed 51.6 billion VND, reaching nearly 12.9% and while waiting for the Advisory Council to resolve the bidding proposal.
According to the Ca Mau Province Construction Project Management Board, the project is delayed due to the organization of bidding, bid evaluation and land clearance of 183 square meters, because the people have not allowed the contractor to dismantle the site for leveling and compacting.