In December, Vietnam National Coal - Mineral Industries Group (TKV) set a target of producing 4.3 million tons of raw coal; excavating 13.27 million m3 of earth and rock; digging 24,720 m3 of tunnels; consuming 4.639 million tons of coal... determined to complete all production and business plan targets for 2024.
That was the direction of Mr. Nguyen Huy Nam, Deputy General Director of TKV, Director of the Production Control Center in Quang Ninh when chairing the conference to deploy the coal production and consumption plan for December.
The conference was attended by Mr. Pham Hong Thai, Deputy Secretary of the Quang Ninh Coal Party Committee; Deputy Director of the Production Management Center in Quang Ninh Nguyen Manh Diep and representatives of leaders of production, logistics, screening, coal consumption units...
Mr. Nguyen Huy Nam chaired the conference to deploy the coal production and consumption plan for December.
In November 2024, units continued to boost production, carry out the emulation movement of 90 days and nights of peak production labor in the fourth quarter, and strive to achieve production and business plan targets.
Accordingly, raw coal production was 3.4 million tons, cumulatively reaching 88% of the yearly plan in 11 months (14/18 coal production units completed and exceeded the monthly plan); earth and rock excavation was 14.47 million m³, reaching 101.4% of the monthly plan, cumulatively reaching 87% of the yearly plan; tunnel excavation was 24,761 m, equal to 104.7% of the monthly plan, cumulatively reaching 84.2% of the yearly plan in 11 months (12/13 coal production units completed and exceeded the monthly plan).
In November, TKV consumed more than 4.65 million tons of coal, equal to 102.6% of the monthly plan, of which coal for electricity production reached 3.842 million tons, equal to 104.7% of the monthly plan...
According to the December plan, TKV aims to produce 4.3 million tons of raw coal; excavate 13.27 million m3 of earth and rock; dig 24,720 m3 of tunnels; consume 4.639 million tons of coal...
Contributing opinions at the conference, the group's professional boards and units focused on participating in the contents of directing and operating production and consumption, implementing technical and technological indicators, ensuring occupational safety and hygiene, environment, difficulties and problems in production, etc.
Directing the conference, Mr. Nguyen Huy Nam, Deputy General Director of TKV, Director of the Operation Center in Quang Ninh, emphasized that December is an important month, deciding the production results of the whole year.
Units continue to focus on closely following the assigned plan, maintaining the spirit of emulation for 90 days and nights of production with the highest determination to boost production, achieve maximum output, strive to achieve the highest production and business results in December, and complete the 2024 plan targets.
In addition, Mr. Nguyen Huy Nam also requested units to focus on promoting tunnel digging and excavation of soil and rock to prepare for production in 2025; pay special attention to ensuring safety in production, inspecting, urging, and motivating production units to implement occupational safety and hygiene; strengthen the work of ensuring safety and order, protecting mine boundary resources, environmental work, and preventing fires and explosions in the dry season...