How is the construction progress of 500kV line 3 through Ha Tinh?

Báo Tuổi TrẻBáo Tuổi Trẻ01/08/2024


Tiến độ thi công đường dây 500kV mạch 3 qua Hà Tĩnh ra sao?- Ảnh 1.

Construction workers at column 174 - Photo: LE MINH

On August 1, at column 175 in Cam Thach commune (Cam Xuyen district, Ha Tinh), workers of Song Da Construction and Service Joint Stock Company were joining the last steel braces to complete the column.

Column 175 is one of the three tallest columns in the 500kV transmission line project through Ha Tinh province. The column is 145m high and weighs 426 tons. Construction began in early 2024. According to schedule, the column installation will be completed in about 3 days.

Tiến độ thi công đường dây 500kV mạch 3 qua Hà Tĩnh ra sao?- Ảnh 2.

Column 175 is one of the three tallest columns in the 500kV line 3 project through Ha Tinh province - Photo: LE MINH

Mr. Bui Van Quang - in charge of the construction team of column 175 - said that the unit has been working at full speed to construct column 175. Up to now, the most difficult stages in the process of assembling the column have been completed. However, in the coming days, the wire pulling stage will also face many challenges. The column is very high, so transporting equipment and wire ends to the column requires specialized machinery.

Tiến độ thi công đường dây 500kV mạch 3 qua Hà Tĩnh ra sao?- Ảnh 3.

Mr. Bui Van Quang is in charge of the construction team of column 175 - Photo: LE MINH

It is expected that the wire pulling at column 175 will take about 10 days. The construction team is currently performing the steps of laying the wire, installing the porcelain chain, and transporting the winch system to the site.

Not far away, a group of about 20 workers from Song Da Construction and Service Joint Stock Company are also doing the final work at column position 174. The group of workers is divided into 2 groups. One group assembles the column frame. The other group connects the porcelain strings together to transport them to the completed column for wire pulling.

Tiến độ thi công đường dây 500kV mạch 3 qua Hà Tĩnh ra sao?- Ảnh 4.

Workers assemble columns at position 174 - Photo: LE MINH

Mr. Nguyen Van Ti - technical officer of Song Da Construction and Service Joint Stock Company - said that this is the location of the 2-body anchorage column (double column) with a height of 56m and a weight of 235 tons. The column was started in February 2024. Currently, the unit is speeding up the progress to pull the wire to hand over to the project investor before September 2.

According to the Central Power Project Management Board, the 500kV 3-circuit line project from Quang Trach to Quynh Luu through Ha Tinh, 141.52km long with 285 column foundations passing through 9 districts and towns, was started in January 2024.

As of July 30, the project in Ha Tinh has completed casting 285 foundation positions, erected 249 columns, and is erecting 36 columns...

Nnững vị trí cột đã hoàn thành việc kéo dây trên địa bàn tỉnh Hà Tĩnh - Ảnh: LÊ MINH

Pole positions where wire pulling has been completed in Ha Tinh province - Photo: LE MINH

According to the Department of Industry and Trade of Ha Tinh province, recently, the People's Committees of districts and towns where the project passes have established working groups to promptly support, resolve and remove difficulties and problems arising at the site so that the 500kV line 3 project can ensure urgent progress according to the direction of the Prime Minister.

Localities have also mobilized available resources, provided maximum support, and created all conditions for investors, contractors, and construction units to best organize logistics, food, accommodation, living, and travel to ensure convenience, hygiene, safety, and health for officers, engineers, workers, and laborers; and ensure security and order.

Đường dây 500 kV mạch 3 chính thức truyền tải điện 500 kV line circuit 3 officially transmits electricity

At 6:00 a.m. this morning, August 17, the National Power Transmission Corporation (EVNNPT), the Central Power Project Management Board (CPMB), in coordination with related units, officially energized the 500kV Vung Ang - Quang Trach line.



Source: https://tuoitre.vn/tien-do-thi-cong-duong-day-500kv-mach-3-qua-ha-tinh-ra-sao-20240801162407879.htm

Comment (0)

No data
No data

Same tag

Same category

Vietnam calls for peaceful resolution of conflict in Ukraine
Developing community tourism in Ha Giang: When endogenous culture acts as an economic "lever"
French father brings daughter back to Vietnam to find mother: Unbelievable DNA results after 1 day
Can Tho in my eyes

Same author

Image

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product