Welcoming the 79th anniversary of the August Revolution and National Day September 2, at key construction projects of the province and the country, the atmosphere of labor competition is taking place vigorously. Overcoming difficulties, contractors, construction units, teams of engineers and workers have been determined to speed up the progress of the projects.
The Van River Bridge project under the Van River Overpass and Western Access Road Construction Investment Project is being urgently completed. Photo: Anh Tuan
After 8 months of urgent construction with the spirit of "overcoming the sun, overcoming the rain", "3 shifts, 4 crews", "only talking about work, no backtracking", close and effective coordination and cooperation between construction forces, the construction project of the 500kV line circuit 3 from Quang Trach (Quang Binh) to Pho Noi (Hung Yen) was completed to be energized at the end of August 2024, practically celebrating National Day September 2.
The 500 kV line 3 project (from Quang Trach, Quang Binh to Pho Noi, Hung Yen) consists of 4 projects with a total length of about 515 km, passing through 9 provinces, including Ninh Binh. Specifically, the project passes through 11 communes of Kim Son district with 21 pole locations, with a length of 7.83 km. The land use area of the project is 3.79 ha, affecting 93 households whose land was recovered for pole bases and 24 households whose power line corridors were affected.
Comrade Duong Duc Dang, Director of the Department of Industry and Trade, affirmed: Ninh Binh has quickly taken action to seriously implement related tasks such as: Agreement on route direction, site clearance, support for construction contractors... especially the site clearance compensation work has been given strong attention and direction; propaganda and mobilization work for households and individuals whose land has been recovered has been promoted.
By January 15, 2024, Ninh Binh province had handed over all 21/21 pole locations and by March 30, 2024, Ninh Binh province had completed the handover of 9/9 anchoring spaces, being the first province among the 9 provinces with the line passing through to complete the handover of the site and anchoring spaces to the investor, creating conditions for the construction unit to soon have the site to implement the project.
After completing the handover of the site, Ninh Binh province exploited the "4 on-site" advantages (on-site command; on-site forces; on-site means and materials; on-site logistics) to support and contract the implementation of simple stages in the construction of the foundation and foundation of the project such as digging soil, digging pillar holes according to the design drawings, helping the investor shorten the project construction time. This has contributed significantly to the construction unit completing and organizing the energization of the 500kV Nam Dinh I-Thanh Hoa line on June 30, according to the set schedule.
The representative of the investor, the National Power Transmission Corporation (EVNNPT), said: The implementation process of the 500 kV transmission line project, circuit 3, Thanh Hoa - Nam Dinh I, has always received the attention and close direction of the Prime Minister, ministries, branches, leaders of EVN, EVNNPT and the consensus and support of local authorities where the project passes through.
As planned, the inauguration ceremony of the 500kV line 3 project from Quang Trach to Pho Noi will be held at the end of August 2024. This is the result of the spirit of solidarity, unity, and the participation of the entire political system, affirming that nothing is difficult and nothing is impossible. The spirit of "overcoming the sun and overcoming the rain" has also spread to the construction sites of key projects in the province.
At the Van River Overpass and Western Van River Access Road Construction Investment Project, dozens of engineers and workers of the construction contractor are urgently carrying out important technical steps to complete the Van River Bridge, contributing to the celebration of the successful August Revolution and National Day September 2.
According to Mr. Nguyen Quang Minh, Deputy Director of the Department of Transport: The project to invest in the construction of the Van River overpass and the western approach road to the Van River, Ninh Binh province is invested by the Department of Transport with a total investment of 340 billion VND. The goal is to gradually complete the traffic infrastructure according to the plan; strengthen the connection of urban subdivisions of the city; connect the North-South Expressway with National Highway 1 and the Ninh Binh City bypass (DT.477 extension) to ensure seamless, continuous traffic from the North-South Expressway through the center of Ninh Binh city; reduce traffic congestion in the city, promote the socio-economic development of Ninh Binh city in particular and Ninh Binh province in general.
The project has completed site clearance, completed the substructure, poured the bridge deck, completed the installation of the architectural arch and is completing the remaining items of the concrete bridge. For the road section, the hard asphalt concrete layer of the route and the intersections of National Highway 1 and Nguyen Hue has been completed, and the road surface and traffic safety system are being prepared for completion. The estimated value of construction and installation is 162 billion VND, reaching 86.9% of the total value, the disbursement rate is 84.2% of the capital allocation plan.
As for the Van River Overpass project, according to the design, it has a length of 64.69m, the approach roads at both ends of the bridge are over 366m, the road surface is made of asphalt concrete. In addition, it will build an architectural arch system; lighting system, landscape, flower garden, trees and other related items. This is the most important item of the project, so it is carefully invested in both technology and aesthetics to ensure that the completed project will be an urban architectural highlight.
Deputy Director of the Department of Transport Nguyen Quang Minh added: The investment project to build the Van River overpass and the western approach road of the Van River is a multi-purpose project, of important significance, of strategic nature, which the Provincial Party Committee's Standing Committee has focused on directing to accelerate progress during the term in order to create a synchronous and modern urban traffic infrastructure, not only opening up space, room, opportunities, and new driving force for the development and breakthrough of the province and localities but also creating space, urban landscape, creating architectural highlights as well as developing inner-city tourism, gradually realizing the development perspective of "taking tourism and cultural industry as the spearhead" and Ninh Binh becoming a centrally-run city with the characteristics of a Millennium Heritage City and a creative city.
The vibrant competitive atmosphere at key construction sites of the country and the province is a good sign contributing to new steps forward for Ninh Binh in completing the transport infrastructure system, creating momentum for comprehensive socio-economic development of the province.
Nguyen Thom
Source: https://baoninhbinh.org.vn/soi-noi-khi-the-thi-dua-tren-cac-cong-trinh-trong-diem/d2024083008400260.htm