Vietnam.vn - Nền tảng quảng bá Việt Nam

Dak Nong is full of key projects

Việt NamViệt Nam28/03/2025


Mostly behind schedule

Dak Nong is currently implementing nearly 80 projects, including transitional and newly opened ones. Of these, 6 major projects are identified as key projects.

Specifically, the Dao Nghia - Quang Khe Road Project Phase 2; Dak Nong Provincial General Hospital Upgrade Project; Gia Nghia City Central Square Project; Relocation and resettlement project for 212 households in the central area of ​​Gia Nghia City; Dak Nong Provincial Museum, Library and Park Complex Project; North-South Expressway Project, West section Gia Nghia (Dak Nong) - Chon Thanh (Binh Phuoc).

library(1).jpg
The Dak Nong Provincial Museum, Library and Park Complex project has just disbursed 79.1/124.7 billion VND.

For various reasons, most projects are currently behind schedule. The Dao Nghia – Quang Khe Road Phase 2 project is an example.

The project was approved by the Dak Nong Provincial People's Committee in Decision No. 2367, dated December 31, 2021. The project has a total investment of VND 830 billion in phase 2. The length of the route is about 25.77km. Implementation period is 2022 - 2025.

The project has 3 packages, including: package 16, package 17, package 18. Of these, packages 17 and 18 are stuck in site clearance. By the end of March 12, 2025, the project has disbursed 249 billion VND/830 billion VND of capital.

Currently, the remaining capital for 2024 of the project of 148 billion VND is proposing to extend the disbursement period to December 31, 2025. The capital plan for 2025 of 285 billion VND has not been disbursed yet.

Dao Nghia - Quang Khe road project phase 2 still stuck in site clearance
Dao Nghia - Quang Khe road project phase 2 has just disbursed 249/830 billion VND

Similarly, the Gia Nghia City Central Square Project was approved by the Provincial People's Committee in Decision No. 1328, dated August 11, 2022. The total investment is 400 billion VND from the central budget. The project started construction on December 27, 2022.

To date, the completed construction volume has reached about 62% of the contract value. The disbursement progress until the end of 2024 is 259/400 billion VND. In 2025 alone, the project was allocated nearly 141 billion VND but has not been disbursed.

The Dak Nong General Hospital Upgrade Project has a total investment of 753 billion VND. To date, the completed construction volume has reached about 50% of the contract value.

Disbursed capital reached 474/752 billion VND. In 2025 alone, the project was allocated 270 billion VND but has not yet been disbursed.

Many knots

Many key projects in Dak Nong have slow disbursement progress due to various reasons. Among them, site clearance is the biggest bottleneck. Of the 6 key projects, 5 projects are stuck in site clearance and need to be quickly resolved.

qt(1).jpg
Gia Nghia City Central Square Project

For example, in the project of the Provincial Park, Museum and Library Complex, currently, there are still 12 households carrying out the site clearance work. However, there is still no specific land price applied to the plan for the Gia Nghia City People's Committee to appraise and approve.

The Dao Nghia-Quang Khe road project includes 3 construction packages, including: package 16, package 17, package 18. Of these, packages 17 and 18 are stuck in site clearance.

Of which, package 17 has a clearance area of ​​30.76 hectares for 76 households and 4 organizations. Package 18 has 295 households and 4 organizations, with an area of ​​40.89 hectares.

Similarly, the Gia Nghia City Central Square Project currently has about 10.59 hectares, but Gia Nghia City has just handed over 2.78 hectares in the core area for construction.

The remaining 7.81 hectares of parking lots, security houses, and public toilets have not been handed over by the city. This greatly affects the progress.

Director of Dak Nong Province's Construction Investment Project Management Board, Ha Sy Son, said that the most difficult part in implementing key projects is site clearance.

hospital
Dak Nong Provincial General Hospital Upgrade Project

“For the Dao Nghia-Quang Khe project, the unit is coordinating with Gia Nghia City and Dak R'lap District to mobilize households to hand over land for construction. As for the Central Square project, the unit is coordinating with the Gia Nghia City Land Fund Management and Development Board to conduct both land inventory and mobilize people to hand over land,” said Mr. Son.

Along with site clearance, lack of earth filling materials is also a factor affecting the progress of projects. The Gia Nghia City Central Square project currently has an earth filling volume of about 70,500m3 that has been coordinated from various sources for the project but has not yet completed the legal procedures. This leads to no basis for acceptance by the contractor and the next step of construction.

NEW INFOR BOARD

In addition to difficulties in site clearance, during implementation, some projects were stuck with bauxite planning, affecting the progress of many projects.



Source: https://baodaknong.vn/dak-nong-ngon-ngang-cong-trinh-trong-diem-247527.html

Comment (0)

No data
No data

Same tag

Same category

Dien Bien girl practiced parachuting for 4 months to get 3 memorable seconds 'in the sky'
Memories of Unification Day
10 helicopters raise the flag in practice to celebrate 50 years of national reunification
Proud of war wounds after 50 years of Buon Ma Thuot Victory

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product