Today, July 31, at An Loi village, Trieu Do commune, Trieu Phong district, a high-point campaign was launched to carry out site clearance for key projects in the district.
Leaders of Trieu Phong district presented gifts to 6 households in An Loi village, Trieu Do commune affected by the coastal road project connecting the East-West Economic Corridor - Photo: Canh Thu
At the launching ceremony, the district leaders called on agencies, departments, branches, and organizations from the district to the grassroots level; Party committees, authorities, fronts, and organizations of communes and towns in the district in general and Trieu Do commune in particular to promote the spirit of responsibility, solidarity, consensus, actively respond and participate in launching the peak period of site clearance for key projects in the district with a spirit of high solidarity and unity in the political system from the district to the grassroots level, taking the work of propagating and mobilizing the people as the main focus, paying attention to ensuring the legitimate interests of the people, along with raising the sense of responsibility, creating high consensus, contributing to the successful implementation of the peak period of site clearance for projects to ensure the goals and plans.
Peak period is from July 31 to August 31, 2024.
It is known that the key projects that need to be implemented on this occasion include: Coastal road connecting the East-West Economic Corridor of Quang Tri province - phase 1; Road connecting An Mo bridge to the Memorial Site of General Secretary Le Duan; Hung Vuong road connecting the East-West Economic Corridor and the Southeast Economic Zone of Quang Tri; Traffic system connecting Ai Tu town with key economic areas of Trieu Phong district; Upgrading and expanding the fishing port combined with the Nam Cua Viet storm shelter anchorage area, Trieu Phong district.
Particularly, the coastal road project connecting the East-West Economic Corridor, Quang Tri province - phase 1, the section passing through Trieu Phong district has a route length of 9.5 km; the total area recovered for project implementation is 617,598 m2 / 1,002 plots of land; there are 468 affected cases. The Compensation, Support and Resettlement Council of Trieu Phong district organized to collect opinions on the compensation and support plan for affected households. The households highly agreed with the proposed plan.
As of June 24, 2024, Trieu Phong district has recovered land with an area of 260,055 m2 , approved compensation plans, and supported 281 households/6 phases with a budget of over 44 billion VND. Currently organizing the payment of compensation and support costs for affected households.
Particularly, the Thach Han 1 Bridge project connecting the Coastal Road connecting the East-West Economic Corridor of Quang Tri province - phase 1 through Trieu Do commune has a total land acquisition area of 48,136 m2 /95 plots; there are 92 affected cases, it is expected to arrange resettlement for 22 households; the compensation and support plan has been approved for 53 households affected by fertile land, handing over 0.4 km for the construction of Thach Han 1 Bridge from pillar T4 to pillar T14. Trieu Phong district strives to complete the project's site clearance work by the end of 2024.
At the launching ceremony, Trieu Phong district presented gifts to encourage 6 households in An Loi village, Trieu Do commune affected by the project.
Minh Kha - Canh Thu
Source: https://baoquangtri.vn/trieu-phong-phat-dong-ra-quan-cao-diem-giai-phong-mat-bang-cac-cong-trinh-trong-diem-187279.htm