Steel arch bridge of 2,200 billion project in Hue "sprints" to completion

Báo Giao thôngBáo Giao thông04/03/2025

The main construction items of the steel arch bridge project of the 2,200 billion VND project in Hue have reached about 95%, the contractor is urgently constructing railings, sidewalks on the bridge; installing power lines and traffic lighting systems...


According to the Hue City Traffic Construction Investment Project Management Board, up to now, the construction progress of the main items of the Huong River overpass project has reached about 95%.

Currently, the contractor is constructing railings and sidewalks on the bridge; installing electrical lines, traffic lighting systems, and decorative lighting systems.

Cầu vòm thép thuộc dự án 2.200 tỷ ở Huế

The contractor is constructing the railings and sidewalks on the bridge; installing power lines and traffic lighting systems...

In addition, the units are speeding up the construction of asphalt concrete pavement (expected to be completed on March 8) and construction of stone pavement items on the bridge; installation of railings on the main bridge...

On March 4, Mr. Nguyen Van Phuong - Chairman of Hue City People's Committee and leaders of departments and branches inspected and urged the construction progress of the Huong River overpass project belonging to Nguyen Hoang Street project and Hue City Cultural - Sports Square project.

Through on-site inspection, listening to the investor and units report on the construction progress, difficulties and obstacles in the implementation process, the Chairman of Hue City People's Committee highly appreciated the efforts of the project implementing units, and at the same time requested the construction units to speed up the progress, ensure the quality of the project as well as labor safety, and soon bring the project to the finish line as planned.

Cầu vòm thép thuộc dự án 2.200 tỷ ở Huế

The Chairman of Hue City People's Committee inspected the construction site of the Huong River overpass project, requesting the investor and construction units to speed up progress, ensure construction quality and labor safety.

The Huong River Overpass under the Nguyen Hoang Road project is a steel arch bridge designed with 5 girder spans, the bridge width is 43m including: 2x3 car lanes 3.5m wide, 2 motorbike lanes 3.5m wide and safety strips in each direction of traffic; 3m wide pedestrian lanes are arranged at different levels on both sides of the bridge.

On the ground, the sidewalks branch down to the park on both sides of the river by 4 curved branch bridges.

The project has a total investment of more than 2,200 billion VND, starting on December 23, 2022, with the Hue City Traffic Construction Investment Project Management Board as the investor.

The joint venture of contractors Trung Chinh Construction and Trading Company Limited - Thua Thien Hue Construction and Management Joint Stock Company - Viet Anh Import-Export Trade Construction Investment Joint Stock Company - Thua Thien Hue Road I Joint Stock Company will carry out the construction within 3 years.

The project investor and contractor are focusing on speeding up progress, striving to complete technical traffic opening on March 26.

Cầu vòm thép thuộc dự án 2.200 tỷ ở Huế

The Huong River overpass project, part of the Nguyen Hoang Street and Huong River overpass project, Hue City, is under construction.

Hue City Cultural and Sports Square Project is a key project, an important cultural and sports institution of the city.

Through inspection, Hue City leaders requested units to focus on human resources and equipment to strive to complete important items and put them into use before March 26, with priority given to completing technical infrastructure items and the exterior of the stadium.

In particular, focusing on ensuring quality, technique, aesthetics, environmental sanitation, construction safety and landscape of the Hue City Cultural and Sports Square project area.

According to the approved decision, the Hue City Cultural and Sports Square project has a total investment of 196 billion VND, with the Hue City Urban Development and Construction Investment Project Management Board as the investor.

The investment objective of building Hue City Cultural - Sports Square is to renovate and embellish the Ba Trieu stadium area in order to gradually complete public cultural and sports facilities to serve the people, orient the development of urban space, harmoniously connect the landscape architecture system, contribute to improving spiritual life, promote socio-economic development of Hue City.



Source: https://www.baogiaothong.vn/cau-vom-thep-thuoc-du-an-2200-ty-o-hue-chay-nuoc-rut-hoan-thien-192250304162818209.htm

Comment (0)

No data
No data

Same tag

Same category

Wandering around Lach Bang beach village
Explore Tuy Phong color palette
Hue - The capital of the five-panel ao dai
Colorful Vietnamese landscapes through the lens of photographer Khanh Phan

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product