Major contractor digs tunnel, opens highway

Việt NamViệt Nam03/09/2024


The National Day holiday on September 2 has not ended yet, but these days, nearly 400 employees and 125 locomotives and equipment of Deo Ca Group are still working hard, accelerating the main items with the spirit of "holiday like normal day", "3 shifts, 4 crews" racing against the weather.

Nhà thầu lớn xuyên lễ đào hầm, thông đường cao tốc- Ảnh 1.

Construction of a tunnel through the mountain on the Dong Dang - Tra Linh highway.

“Everyone is focusing on the construction of the following items: 2 tunnel branches through the mountain, the access road, bored pile construction, girder casting… This is an extremely difficult project, which the people and local authorities have been looking forward to for many years.

"The staff, engineers and workers of Deo Ca Group always take advantage of every hour, encouraging each other to work with the determination to bring the project to the finish line on time," said Mr. Nguyen Duc Tuan, Director of Dong Dang - Tra Linh Project Management Board.

In the exciting atmosphere when the results of the first layer of asphalt concrete construction test were accepted and approved by the investor and consultant, right on the occasion of September 2nd holiday, thousands of workers of Deo Ca Group at the XL01 package of the Quang Ngai - Hoai Nhon expressway project stuck to the construction site to mass-construct the asphalt concrete items.

Nhà thầu lớn xuyên lễ đào hầm, thông đường cao tốc- Ảnh 2.
Nhà thầu lớn xuyên lễ đào hầm, thông đường cao tốc- Ảnh 3.

Deo Ca Group workers worked through the night to speed up construction progress on the Quang Ngai - Hoai Nhon expressway section.

Mr. Tran Van Chi, Executive Director of XL01 package, said that at the construction site, Deo Ca Group is mobilizing 3 asphalt concrete paving systems, each consisting of a paver, four rollers, 30 asphalt concrete transport trucks, and dozens of engineers and workers working continuously to ensure progress.

“Determining that the remaining workload is very large, and the construction area is about to enter the rainy season, the contractor has encouraged staff and workers to be on duty 100% and work overtime during the holidays to take full advantage of favorable weather days to construct important items.

"The treatment for workers is guaranteed to be commensurate with their labor force, with a salary of 300% compared to normal days," Mr. Chi shared.

Also on this occasion, the Management Board of Package XL01 of the Chi Thanh - Van Phong project arranged 50 workers to be on duty day and night at the construction site to ensure that the construction progress is not interrupted.

Nhà thầu lớn xuyên lễ đào hầm, thông đường cao tốc- Ảnh 4.

Deo Ca Group constructs Chi Thanh - Van Phong expressway.

According to Mr. Truong Cong Dat, Director of the XL1 Package Management Board, at the Chi Thanh – Van Phong section project, construction continues to face difficulties due to complicated geological conditions. However, engineers and workers still uphold the spirit of overcoming challenges to increase production.

“Up to now, within the scope of Deo Ca Group's construction, the completed output has reached nearly 56% of the contract value, exceeding the plan by 8%,” said Mr. Dat.

Racing against the weather, nearly 80 engineers and workers of the XL1 package of the Khanh Hoa - Buon Ma Thuot expressway are also busy working, speeding up the progress of the projects: Phuong Hoang tunnel, Song Cho bridge and Cua Tay bridge.

Mr. Nguyen Viet Chung, Commander of Phuong Hoang Tunnel, said that even though it was a holiday, the officers, engineers, and workers of Deo Ca Group still maintained a serious and urgent working spirit.

As for the Phoenix Tunnel project - the longest road tunnel on the Khanh Hoa - Buon Ma Thuot expressway, the current progress of digging the left and right tunnel branches has reached 160m and 121m respectively. The target is that by December 2025, the tunnel will be opened, 6 months ahead of the overall project schedule.

Nhà thầu lớn xuyên lễ đào hầm, thông đường cao tốc- Ảnh 5.

Workers of Deo Ca Group stay at the construction site during the holidays, speeding up the construction progress of the bridge on the Tuyen Quang - Ha Giang highway.

Meanwhile, at the XL24 package of the Ha Giang - Tuyen Quang expressway project, checking the progress of the packages, Mr. Nguyen Thien Tuyen, Director of the Traffic Project Management Board of Tuyen Quang province, highly appreciated the proactive spirit of the contractor in solving difficulties and the enthusiasm of the engineers and workers who put aside the joy of family reunion to stay at the construction site to work during the holidays.

It is known that, to ensure the project progress, Deo Ca Group has established Construction Command Boards at the bridge points, proactively coordinating machinery, equipment and personnel to serve the construction at the locations where the site has been handed over.

The goal in 2025 is to complete all 20 bridges on the Tuyen Quang - Ha Giang expressway by Deo Ca.

Source: https://www.baogiaothong.vn/nha-thau-lon-xuyen-le-dao-ham-thong-duong-cao-toc-192240903114825785.htm


Comment (0)

No data
No data

Same tag

Same category

Explore Lo Go - Xa Mat National Park
Quang Nam - Tam Tien fish market in the South
Indonesia fired 7 cannon shots to welcome General Secretary To Lam and his wife.
Admire the state-of-the-art equipment and armored vehicles displayed by the Ministry of Public Security on the streets of Hanoi

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product