Following the direction, the Highway 5 repair construction unit has added 2 more people to guide and direct traffic in the repair area (previously only 1 person was assigned). At the same time, the construction is organized in short sections, avoiding construction during rush hours, and organizing construction at night. When the number of vehicles participating in traffic on the route is high, the construction is temporarily stopped...
Currently, Highway 5 has repaired 28 km out of a total of 30 km of road surface, and is repairing the remaining 2 km of road surface. Some of the repair locations are intersection areas, with heavy traffic and people, posing many potential traffic safety risks.
From June 20 to the afternoon of June 24, on National Highway 5 through construction and repair areas, vehicles moved slowly but there was no traffic jam.
National Highway 5 through Hai Duong has a large number of people and vehicles, always posing a risk of traffic safety and congestion. On the afternoon of June 19, on National Highway 5 through Kim Thanh district, there was a traffic jam that lasted for many hours, affecting the movement of vehicles and the lives and activities of people in the area.
On June 20, 2024, Comrade Luu Van Ban, Member of the Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Committee chaired a meeting with relevant units and sectors on ensuring traffic order and safety and preventing congestion on National Highway 5.
PVSource: https://baohaiduong.vn/sau-chi-dao-quoc-lo-5-doan-qua-hai-duong-dang-sua-chua-da-het-un-tac-385423.html