Proposal to invest more than 345 billion VND to build a national highway 5 service road through Cam Giang

Việt NamViệt Nam09/10/2024


img_2235.jpg
Chairman of Hai Duong Provincial People's Committee Le Ngoc Chau chaired the October meeting (2nd time)

According to the report of the Department of Planning and Investment, the National Highway 5 service road project must be from Ghe intersection to Lai Cach intersection (km40+240-km43+870) the remaining sections and from Lai Cach commercial urban area to the end of Cam Binh Shoe Company on the left side of the route (km44+205 - km44+795).

img_2257.jpg
Standing Vice Chairman of the Provincial People's Committee Luu Van Ban requested the Department of Planning and Investment and Cam Giang district to review the total investment of the project, especially the cost of site clearance.

The project investment objective is to synchronously connect the feeder road sections in Cam Giang district, enhance the exploitation capacity, ensure traffic safety, improve travel conditions, reduce congestion and traffic accidents on National Highway 5; create convenience for people and businesses in the area to live and do business; gradually complete the feeder road system along both sides of National Highway 5 through Cam Giang district and Hai Duong province; contribute to attracting investment and developing the socio-economy of Cam Giang district in particular and Hai Duong province in general.

chau.jpg
The leader of the Department of Planning and Investment reported on the proposed investment policy for the project.

Accordingly, the right-hand side of Highway 5 from Ghe intersection (km40+240) to Lai Cach intersection (km43+870) consists of 4 sections.

Section 1 has the starting point intersecting with district road 195B (Ghe intersection area at km40+240 of National Highway 5); the end point connects with the service road through Tan Truong industrial park at km40+655 of National Highway 5; length is about L=419.5m.

Section 2 has the starting point connecting to Tan Truong service road (corresponding to km41+815 of National Highway 5). The end point connects to Tan Truong industrial park service road (corresponding to km42 of National Highway 5). The length of the route is about L=178.5m.

img_2266(1).jpg
Cam Giang district leaders report at the meeting

Section 3 has the starting point connecting to Tan Truong service road (corresponding to National Highway 5 at km42+142). The end point connects to the service road through Cam Giang District Treasury (corresponding to km43+120 National Highway 5). The length of the route is about L=985m.

Section 4 starts at the intersection with Nguyen Danh Nho street and the road through Cam Giang district treasury (corresponding to km43+525 of national highway 5). The end point is at the intersection of Lai Cach town (corresponding to km43+870 of national highway 5). The length of the section is about L=301.65m.

img_2263.jpg
Scope of project reporting at the meeting

The left-hand collector road from Lai Cach commercial urban area to the end of Cam Binh Shoe Company on the left side of the route (km44+205 – km44+795 National Highway 5). The starting point of the route intersects with Hoa Binh street in Lai Cach commercial urban area (corresponding to km44+190 National Highway 5). The end point is at Cam Binh Shoe Company area (corresponding to km44+786 National Highway 5). The length of the route is about L=593.5m.

The total length of the above sections is about L=2.48 km, the feeder roads are built according to TCVN 4054:2005 standards (equivalent to level IV - plain roads) in accordance with the approved planning scale. The project uses about 3.22 hectares of land in Cam Giang district.

The total project investment is expected to be over 345 billion VND; implementation period is 2024-2026.

Chairman of the Provincial People's Committee Le Ngoc Chau made a concluding speech that the Provincial People's Committee agreed on the investment policy of the above project, requested the Department of Planning and Investment, Department of Transport and Cam Giang district to absorb the opinions of the leaders of the Provincial People's Committee, departments and branches at the meeting, continue to review the total investment, especially the site clearance cost, and estimate that if the cost arises, it will still be in the reserve. Assign the Provincial People's Committee Office to complete the draft to report to the Party Committee and submit to the Provincial Party Committee Standing Committee.

At the meeting, the Hai Duong Provincial People's Committee also considered the draft proposal submitted to the Provincial People's Council by the Hai Duong Department of Health on the Regulation on the quantity and level of monthly support for medical staff in villages and residential areas in communes, wards and towns in Hai Duong province. Reviewed reports from the Department of Planning and Investment on the proposal to issue a Decision on the List of land plots for bidding to select investors using land in Hai Duong province; reported on the proposal to adjust the investment policy of the projects: Investment in the construction of the road and Van bridge connecting National Highway 37 from Chi Linh city to the approach road to Trieu bridge, Kinh Mon town; Investment in the construction of the extended Provincial Road 396 (the section connecting from Provincial Road 391 to Provincial Road 390); Upgrading and expanding Provincial Road 391 from Hai Duong city to the East-West axis road, Hai Duong province; reported on the proposal for the investment policy of the Project to build a new evidence warehouse of the Civil Judgment Enforcement Agency of Hai Duong province. Review the report on the zoning plan for Hoang Dieu Industrial Park, Gia Loc District, scale 1/2000 of the Department of Construction.

BANK


Source: https://baohaiduong.vn/de-xuat-dau-tu-hon-345-ty-dong-xay-dung-duong-gom-quoc-lo-5-qua-cam-giang-395219.html

Comment (0)

No data
No data

Same tag

Same category

Overseas Vietnamese player Le Khac Viktor attracts attention in Vietnam U22 team
The creations in the TV series 'Remake' left an impression on Vietnamese audiences
Ta Ma - a magical flower stream in the mountains and forests before the festival opening day
Welcoming the sunshine in Duong Lam ancient village

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product