Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed

Báo Tiền PhongBáo Tiền Phong29/02/2024


After more than 2 years of construction, the Dong Nai riverside road connecting Hoa An bridge (Bien Hoa city, Dong Nai) to Vinh Cuu district is gradually being completed, bringing a new look to Bien Hoa city.

Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed photo 1

Panoramic view of the Dong Nai riverside road worth nearly 2,000 billion VND under completion.

The Dong Nai riverside road is 5.2km long, with a total investment of nearly 2,000 billion VND, and was started at the end of December 2021. This includes the investment project to build a riverbank embankment with a cost of more than 600 billion VND.

Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed photo 2
Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed photo 3

According to VietNamNet, in late February 2024, workers at the construction site along the Dong Nai River were still rolling the roadbed, grading crushed stone, drilling bored piles, driving riverbank embankment piles, installing railings,...

Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed photo 4

A resident has not yet relocated and handed over the site to the construction unit.

However, up to now, the land for handover of the Dong Nai riverside road construction has reached 79%, the construction progress has reached 57%. The main reason for the project's delay is due to the land clearance work, many generations in a family living on the land have requested additional resettlement quotas.

Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed photo 5

According to the design, the road is 34m wide, with each side sidewalk being 5m wide, and the road surface and median strip being 24m wide. Up to now, many sections have completed the drainage system, and some sections have completed the asphalt, electricity and water.

Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed photo 6Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed photo 7
To implement the project, Bien Hoa City has reclaimed a total area of ​​20.2 hectares from 545 households and 12 organizations, of which 274 households were completely cleared. Up to now, the compensation and site clearance support plan has been approved for 538 households and 12 organizations with an area of ​​15.66/16.19 hectares, with a total cost of about 816 billion VND.

Currently, 462 households and organizations have been paid about 685 billion VND. There are still 7 households that have not approved the compensation and support plan with an area of ​​about 0.53 hectares, costing about 9 billion VND.

Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed photo 8
Mr. Nguyen Ton Trong, Director of Bien Hoa Project Management Board, the investor, said that the project is facing difficulties because some residents do not agree to relocate. In addition, there is still no resettlement area so it is not possible to relocate households.

"There is still a 5-month temporary residence policy for affected households, but if temporary residence is too long or if a family of 5-7 people moves out to rent a place, they will not agree," said Mr. Trong.

Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed photo 9

A section of road has been paved and railings have been installed along the river embankment.

The Dong Nai riverside route not only helps solve traffic congestion but also contributes to promoting socio-economic development in the area, creating an urban landscape highlight for Bien Hoa city and improving the quality of life for people.

Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed, photo 10Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed photo 11
Workers are completing the electrical and water systems.

According to the plan, the entire site will be handed over in the first quarter of 2024, the construction unit of the 5.2 km long Dong Nai riverside road project will be completed in the third quarter and the riverside embankment construction project will be completed in the second quarter.

Appearance of Dong Nai riverside road worth nearly 2,000 billion is about to be completed photo 12

Perspective of Dong Nai riverside road when completed.

According to VietNamNet



Source

Comment (0)

No data
No data

Same tag

Same category

Colorful Vietnamese landscapes through the lens of photographer Khanh Phan
Vietnam calls for peaceful resolution of conflict in Ukraine
Developing community tourism in Ha Giang: When endogenous culture acts as an economic "lever"
French father brings daughter back to Vietnam to find mother: Unbelievable DNA results after 1 day

Same author

Image

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product