HAI PHONG - Ben Rung Bridge across Da Bach River, connecting Hai Phong with Quang Ninh, has completed more than 92% of the construction volume.


Ben Rung Bridge started construction in May 2022. Of the nearly 2,000 billion VND investment, the central budget allocated 1,100 billion VND; Hai Phong City more than 835 billion VND and Quang Ninh province 5.5 billion VND.
After more than 18 months of construction, the bridge has basically taken shape and is expected to be inaugurated on April 30.


The three main pillars across the river are designed in the shape of the letter V (Victory) symbolizing the three victories over foreign invaders on the Bach Dang River.


The bridge is 1.9 km long, 21.5 m wide, has 4 motor lanes and 2 mixed lanes, with synchronous auxiliary infrastructure such as safety strips, median strips, lighting systems, traffic safety equipment, etc.


The project passes through 1.85 hectares of mangrove forest. On the Hai Phong side, one hectare of forest has been handed over. After the project is completed, the authorities will replant the forest.
A year ago, the project was very difficult to carry out because 0.8 hectares of forest in Quang Ninh had to be converted, which took a long time, and the overall project was behind schedule. The construction unit had to build a bamboo bridge for workers to move and support the concrete pipe. After that, the leaders of the two localities met to discuss and implement many measures to complete the site clearance and project construction.
Vnexpress.net
Source link
Comment (0)