'SOS' for a series of projects with no completion date in Ha Tinh

Báo Tiền PhongBáo Tiền Phong26/10/2024

TPO - Many projects have been invested with tens of billions of dong but have not been completed on schedule due to land acquisition problems. Local authorities have repeatedly proposed to the People's Committee of Ha Tinh province and relevant agencies to remove the "bottlenecks" but have not had any results.


TPO - Many projects have been invested with tens of billions of dong but have not been completed on schedule due to land acquisition problems. Local authorities have repeatedly proposed to the People's Committee of Ha Tinh province and relevant agencies to remove the "bottlenecks" but have not had any results.

Close-up of delayed projects, waiting to be “unstuck”. Video: Pham Truong.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 1

The infrastructure project outside the fence of Thach Bang Industrial Cluster (Loc Ha town, Loc Ha district, Ha Tinh) was approved by the People's Committee of Ha Tinh province in October 2021, with a total investment of more than 84 billion VND, from the central budget.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 2

The project started construction at the end of 2022 with many items such as building a new concrete road longer than 1.2km, drainage system, technical trenches and technical sewers; lighting; medium voltage lines; water supply...

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 3

However, up to now, the project is still being constructed "skipping", only a few hundred meters of road have been constructed, and other items have not been implemented due to problems with aquaculture land of households.

'SOS' for a series of projects with no completion date in Ha Tinh photo 4'Calling for help' for a series of projects with no completion date in Ha Tinh photo 5'SOS' for a series of projects with no completion date in Ha Tinh photo 6

According to local authorities, the project is delayed due to the problem of people's aquaculture land area. This area is not subject to compensation according to current regulations, but because people invest in aquaculture with large capital and have been cultivating aquaculture for many years, they hope to have appropriate support policies.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 7

Mr. Tran Xuan Loc - technical officer of the Construction Investment Management Board of Loc Ha district - said that the provincial leaders and departments have come to inspect and discuss, but there are no regulations or appropriate support policies for the people. "The unit is continuing to ask for opinions from the province, hoping to soon have instructions for appropriate handling, helping the project to be implemented again and completed soon," said Mr. Loc.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 8'Calling for help' for a series of projects with no completion date in Ha Tinh photo 9'Calling for help' for a series of projects with no completion date in Ha Tinh photo 10

The project stalled, leaving machinery waiting and components strewn along the road. People had difficulty getting around.

'SOS' for a series of projects with no completion date in Ha Tinh photo 11'Calling for help' for a series of projects with no completion date in Ha Tinh photo 12

The project stalled, leaving machinery waiting and components strewn along the road. People had difficulty getting around.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 13

Next to it is the Ta Nghen Dyke Emergency Treatment Project with a total length of over 10km. The project has a capital of over 180 billion VND. However, after many years of construction, the project is still unfinished.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 14

According to the Management Board of Investment and Construction Projects of Loc Ha District, the project is slow to be implemented due to the land acquisition problems of aquaculture households. Up to now, the locality is looking for solutions to resolve the problems.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 15

These days, some machines continue to work on cleared locations, but the site clearance is still stuck and the project has no completion date.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 16

The infrastructure project of Loc Ha beach tourism area through Thinh Loc commune is also in a similar situation due to land acquisition problems. The project was approved by the People's Committee of Ha Tinh province in July 2017 with a total investment of 62 billion VND with the aim of developing commercial tourism services, attracting investors to the tourist area, and serving tourists.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 17

The project has a scale of 2 routes of more than 3.6 km. However, after many years of implementation, the project has not been completed yet, many locations are stuck with land clearance and cannot be constructed. In the picture, a grave is located right on the route that has not been cleared.

'SOS' for a series of projects with no completion date in Ha Tinh photo 18

The project's implementation was not guaranteed, causing construction materials to overflow into local people's fields.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 19'Calling for help' for a series of projects with no completion date in Ha Tinh photo 20

According to the representative of the Loc Ha District Construction Investment Project Management Board, the construction progress has reached 70%. The unit is speeding up the clearance of the remaining land to bring the project to the finish line. In the picture, many machines are lying idle due to the project being stuck and unable to be implemented.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 21

The Loc Ha coastal rescue road project started construction in May 2020, with the People's Committee of Loc Ha district (Ha Tinh province) as the investor, with a capital of 128 billion VND. The road is 6.5 km long, passing through Loc Ha town, Thach My commune and Phu Luu commune. According to the plan, the project must be completed and put into use by the end of 2021. However, for more than 2 years, the road through Trung Nghia residential group (Loc Ha town) has been "interrupted" because of the cemetery that cannot be cleared.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 22

Loc Ha is a coastal district of Ha Tinh but has all the natural conditions of mountains, plains and sea. The highlight of natural tourism potential is the Bang Son mountain range running along 12 km of coastline and gentle beaches, creating conditions for the development of diverse forms of tourism.

'Calling for help' for a series of projects with no completion date in Ha Tinh photo 23'Calling for help' for a series of projects with no completion date in Ha Tinh photo 24'Calling for help' for a series of projects with no completion date in Ha Tinh photo 25

However, there are still many investment projects here that are slow to implement or unfinished, causing difficulties for local socio-economic development.

Pham Truong



Source: https://tienphong.vn/cau-cuu-loat-du-an-chua-hen-ngay-ve-dich-o-ha-tinh-post1685736.tpo

Comment (0)

No data
No data

Same tag

Same category

Spectacular start of Vietnamese film market in 2025
Phan Dinh Tung releases new song before concert 'Anh trai vu ngan cong gai'
Hue National Tourism Year - 2025 with the theme "Hue - Ancient Capital - New Opportunities"
Army determined to practice parade 'most evenly, best, most beautiful'

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product