3 extensions but still not completed

Việt NamViệt Nam27/12/2023

(QNO) - The DH6b.DX route project connecting the old 129 road (now Vo Chi Cong road) to Duy Hai resettlement area (phase 1) is about 3km long. After many years of construction and time extension, it is still not completed, causing frustration among the people.

Road DH6b.Dx intersection with Thanh Nien street. Photo: PHAN VINH
Road DH6b.DX intersection with Thanh Nien Street. Photo: PHAN VINH

People are angry

Mr. Nguyen Van Ba's house (born in 1954, Tay Son Dong village, Duy Hai commune, Duy Xuyen) has a coffee shop located at the intersection between DH6b.DX route and Thanh Nien road. Since 2021, when the DH6b.DX route project connecting Vo Chi Cong street to Duy Hai resettlement area (phase 1) with a road width of 20.5m with a 2m wide median strip, and sidewalks on each side of the road more than 6m wide, started construction, Mr. Ba and local people knew that the project would be completed in less than 1 year, so they were very excited.

However, up to now, after nearly 3 years, the project is still unfinished, the investment roads are not synchronized, there are still many places that have not been constructed. Right in the area in front of Mr. Ba's coffee shop, it is muddy in the rainy season, and dusty in the dry season.

[VIDEO] - Mr. Nguyen Van Ba ​​reflects on the project's shortcomings:

"This road has been built for too long, some parts are good, some parts are not, there is no street lighting. It is very dangerous for children going to school, workers going home from work in the afternoon. So we hope the government will soon complete the project, synchronize the auxiliary works as previously informed, then people will stop worrying" - Mr. Ba said.

Many sections of the project have not been constructed yet. Photo: PHAN VINH
Many sections of the project have not been constructed for many years. Photo: PHAN VINH

Mr. Ho Nhay (born in 1949, Tay Son Dong village, Duy Hai commune, Duy Xuyen) said that the short road section has been under construction since 2021 and has not been completed yet, making the people here very upset. A road under construction with up to 5 unfinished points is like a bottleneck. The unsynchronized infrastructure also makes it difficult for people to travel, lurking the risk of accidents.

[VIDEO] - Mr. Ho Nhay is concerned about traffic safety:

"Just yesterday (December 25), in my neighborhood, Mr. Quang had an accident on his way home from work. His car was completely destroyed, but luckily no one was hurt. There have been many traffic accidents on this road, with people breaking their legs and arms. Therefore, I hope the government will soon complete the road so that people can travel with peace of mind," said Mr. Nhay.

3 times of extension request still unfinished

According to Mr. Tran Van Siem - Vice Chairman of Duy Hai Commune People's Committee, the project of route DH6b.DX connecting from Vo Chi Cong Street to Duy Hai resettlement area (phase 1) through the commune is invested by the Provincial Traffic Construction Investment Management Board, and has been under construction since 2021.

Project view from above. Photo: PHAN VINH
Project view from above. Photo: PHAN VINH

The project consists of 2 lanes, with a median strip, sidewalks, and lighting. Up to now, the construction units are trying to open the route to 1 lane. However, traffic is still difficult and unsafe.

Mr. Siem suggested: "The locality requests the investor to complete the road soon. And this is also the wish of the people in Duy Hai Resettlement Area because there is currently no smooth road from the main roads to this area. On the upcoming Lunar New Year, we hope the investor will complete it soon to ensure travel for the people."

[VIDEO] - Vice Chairman of Duy Hai Commune People's Committee Tran Van Siem informed about the project:

On December 22, Duy Xuyen District People's Committee had a working session with the Provincial Traffic Construction Investment Management Board on compensation and site clearance for two projects: Road connecting Duy Hai Residential Area to Truong Giang Bridge and DH6.DX route connecting Vo Chi Cong Street to Duy Hai Resettlement Area (phase 1).

Accordingly, regarding the route from Vo Chi Cong Street to Duy Hai Resettlement Area, there is still a problem with the land of Mr. Tran Van Cu and Ms. Nguyen Thi Na's households, the section Km0+240 - Km0+340 because the resettlement area has not been arranged and the compensation, site clearance and resettlement plan is being re-established, so it will be discussed and resolved in April 2024. In addition, the project is still stuck at Km1+815 - Km1+970 of the Le family households and Km2+100 - Km2+710, adding 3,892m2 to the south of the road.

The project has just completed 6m of road surface at the intersection with Thanh Nien Street but it is very dangerous for traffic. Photo: PHAN VINH
The project has just completed 6m of road surface at the intersection with Thanh Nien Street. Photo: PHAN VINH

Previously, on December 8, the Provincial Traffic Construction Investment Management Board sent Document No. 1731/TTr-BQLGT to the Provincial People's Committee and the Department of Transport regarding the consideration and approval of the adjustment of the implementation time of the DX6.DX route project connecting Vo Chi Cong to Duy Hai Resettlement Area (phase 1).

Specifically, the project construction status has completed the concrete road surface at the locations where the site was handed over. The construction value implemented up to the time of preparing the report was 29.1/48.84 billion VND, reaching about 60% of the value. To continue investing in construction, completing the route, promoting investment efficiency, and the project's objectives, the Provincial Traffic Construction Investment Management Board submitted for approval the project implementation period until 2024.

The project is expected to be completed in June 2024. Photo: PHAN VINH
The project is expected to be completed in June 2024. Photo: PHAN VINH

Speaking with reporters from Quang Nam Newspaper, a representative of the provincial Traffic Construction Investment Management Board said that the DH6.DX route project connecting Vo Chi Cong Street to Duy Hai Resettlement Area (phase 1) was constructed by a joint venture of Quang Dai Viet Construction Joint Stock Company and Nghia Thanh Construction Company Limited.

The construction progress of the DH6.DX route project connecting Vo Chi Cong Street to Duy Hai Resettlement Area (phase 1) is 6 months, however, due to site clearance issues, this unit has requested an extension 3 times. It is expected that after the locality hands over the entire site to the project, this project will be completed in June 2024.


Source

Comment (0)

No data
No data

Same tag

Same category

Explore Lo Go - Xa Mat National Park
Quang Nam - Tam Tien fish market in the South
Indonesia fired 7 cannon shots to welcome General Secretary To Lam and his wife.
Admire the state-of-the-art equipment and armored vehicles displayed by the Ministry of Public Security on the streets of Hanoi

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product