On the afternoon of August 17, Prime Minister Pham Minh Chinh inspected the construction progress at the construction site of the Khanh Hoa - Buon Ma Thuot Expressway Investment and Construction Project.
Joining the delegation were Deputy Minister of Transport Le Anh Tuan and representatives of relevant ministries, branches and localities. On the Dak Lak side, there were Central Party Committee member, Provincial Party Secretary Nguyen Dinh Trung; Deputy Provincial Party Secretary, Chairman of the Provincial People's Committee Pham Ngoc Nghi; leaders of the Provincial People's Committee, representatives of departments, branches and localities in the province.
Prime Minister Pham Minh Chinh looks at the map of the Khanh Hoa - Buon Ma Thuot expressway project.
At the bidding packages of the Component 3 project through Krong Pac and Ea Kar districts, Prime Minister Pham Minh Chinh expressed his impression of the construction momentum at the site. At the same time, he encouraged contractors to maximize the spirit of "overcoming the sun and overcoming the rain", "only discussing work, not backtracking", to ensure the progress and quality of the project.
The Prime Minister praised Dak Lak province for taking charge of the expressway project for the first time, but it has made great efforts, and now the expressway has taken shape clearly. Difficult sections on the expressway have also been assigned to the Ministry of Transport and large experienced contractors, from which good experiences have been drawn for the entire project.
Visiting the jobs and lives of cadres, engineers and workers at the construction site, Prime Minister Pham Minh Chinh was impressed with the spirit of hard work and enthusiasm of the workers at the projects.
Prime Minister Pham Minh Chinh talked and encouraged people where the project passed through.
Talking with the people living in the area where the project passes, the Prime Minister expressed his joy that the people agreed and unanimously agreed to let the government carry out the project. The Prime Minister emphasized that this is a key national project, so it is necessary to have the people's sharing and consensus for the common goal...
Prime Minister Pham Minh Chinh presents gifts...
... motivate staff, contractors, and workers on site.
In the coming time, Prime Minister Pham Minh Chinh emphasized that the entire political system must strive to complete the site clearance work, actively participate in directing, mobilizing and encouraging people; and relocate technical works to speed up the construction progress.
The Prime Minister proposed mobilizing Military Region 5, the police force, and the people to support the project in the work that can be done with the spirit of "Once in action, victory is assured".
In addition, it is necessary to strengthen inspection, ensure environmental hygiene, limit dust affecting people's lives, and especially closely cooperate with local people where the project is implemented.
Prime Minister Pham Minh Chinh encouraged and visited workers and laborers at the construction site.
Dak Lak province continues to promote the achieved results, strive to rebuild the critical road on schedule, and strive to complete this expressway section by 2025. The Prime Minister requested to promote the spirit of self-reliance and self-improvement, and not to break up the bid packages. At the same time, it is important to ensure that resettlement areas have better living conditions and at least equal to the old place of residence; take care of the lives and create stable livelihoods for people after giving up land, houses, and fields to build the project. Units need to stay close to the construction site, encourage the working spirit of cadres, engineers, workers and laborers, and create a vibrant competitive atmosphere at the construction site...
Prime Minister Pham Minh Chinh Visit and encourage the staff, contractors, and workers who are constructing the expressway passing through Cu Elang commune, Ea Kar district.
The Khanh Hoa - Buon Ma Thuot Expressway Project is 116.5 km long, with a 4-lane phased scale and a total investment of nearly VND 22,000 billion. The project is divided into 3 component projects and assigned to the People's Committees of Khanh Hoa and Dak Lak provinces and the Ministry of Transport as the managing agencies. The project started in June 2023, and is expected to be basically completed in 2026 and put into operation in 2027.
Up to now, the Khanh Hoa - Buon Ma Thuot expressway project, component project 1 through Khanh Hoa province, the construction and installation value has reached 20%; Component project 2 has a total construction and installation volume value reaching nearly 7% of the value; Component project 3 has reached more than 15% of the value.
Source: https://daklak.gov.vn/-/thu-tuong-chinh-phu-pham-minh-chinh-kiem-tra-tien-o-thi-cong-du-an-uong-bo-cao-toc-khanh-hoa-buon-ma-thuot