The overpass at Ba Bau intersection on National Highway 1 (QL1) connects to Phan Thiet - Dau Giay Expressway, facilitating cars to enter and exit the expressway, avoiding conflicts and traffic congestion at the gateway to Phan Thiet City.
On February 5, Mr. Nguyen Cong Hop, Deputy Director of the Phan Thiet - Dau Giay Expressway Management Board, said that the Thang Long Project Management Board has coordinated with Binh Thuan province to mobilize people to hand over the land to soon start construction of the Ba Bau intersection overpass on National Highway 1.
Ba Bau intersection at Km1717 on National Highway 1 connecting Phan Thiet - Dau Giay Expressway will soon have an additional overpass added (Photo: Vinh Phu).
This is an additional item after the Phan Thiet - Dau Giay expressway is put into operation from the end of April 2023.
"Currently, the Board is completing related procedures to soon start construction of the overpass. If all goes well, the project is expected to start in April 2025," Mr. Hop informed.
According to the approved design, the intersection connecting to National Highway 1 (Ba Bau intersection) was adjusted to an intersection with four branches entering and exiting National Highway 1 from the connecting route and the new Ham Kiem - Tien Thanh route (expressway connecting road), each branch has two lanes.
Build an overpass on National Highway 1 with four lanes, arrange a roundabout under the overpass and expand the existing Suoi Sop bridge.
Add some rural road sections with additional horizontal and vertical drainage systems.
In addition, at Phan Thiet intersection, add a right turn from the highway with a length of 1.2km. Scale of two lanes, road surface width 7m, right shoulder width 3m and left shoulder width 1m.
Busy traffic on Phan Thiet - Dau Giay highway through Binh Thuan province.
Previously, in July 2023, the People's Committee of Binh Thuan province proposed to build an additional overpass at Ba Bau intersection to relieve traffic conflicts.
The solution proposed by this province is to soon invest in building an overpass on National Highway 1, the section passing through Ba Bau intersection (at Km 1717+593, Ham Kiem commune).
At the same time, open a new right-turning branch road from Dau Giay to Phan Thiet before reaching Ba Bau intersection to regulate the flow of vehicles entering and exiting the highway, ensuring safer and more convenient movement.