The Vietnam Road Administration has just issued a document requesting the Thang Long Project Management Board to speed up the selection of investors for the Dau Giay - Tan Phu Expressway Project.
According to the Vietnam Road Administration, the Dau Giay - Tan Phu Expressway construction investment project (phase 1) under the PPP method was approved for investment by the Ministry of Transport (now the Ministry of Construction) in Decision No. 954 dated July 30, 2024.
Performing the task of the inviting party, organizing the selection of investors to implement the project, Thang Long Project Management Board opened the bid on February 27, 2025.
The Dau Giay - Tan Phu Expressway project will create a driving force for connection, promote cooperation and development of the Southeast region with the Mekong Delta, the Central Highlands and the South Central region (Illustrative photo).
To ensure the project's progress, the Vietnam Road Administration requested the Thang Long Project Management Board to promptly complete the evaluation of bidding documents and submit to the Ministry of Construction the results of investor selection.
At the same time, coordinate with relevant agencies to develop a project implementation plan, including a construction commencement plan to meet the progress requirements of the Prime Minister and the Ministry of Construction.
According to the project approval decision of the Ministry of Transport, the Dau Giay - Tan Phu Expressway Construction Investment Project (phase 1) under the PPP method with a total length of more than 60km.
The project starts at Km 0+000, at the intersection with National Highway 1, connecting with Ho Chi Minh City - Long Thanh - Dau Giay Expressway, located in Dau Giay town, Thong Nhat district, Dong Nai province. The end point is at Km 60+243.83 (end of the intersection with National Highway 20), connecting with the Tan Phu - Bao Loc Expressway Construction Project (Lam Dong), located in Phu Trung commune, Tan Phu district, Dong Nai province.
The project has a total investment of more than VND 8,981 billion. The capital mobilized by the investor is about VND 7,681 billion, the planned capital arrangement in 2025 is about 30%, in 2026 about 40%, in 2027 about 30%. The State capital participating in the project is about VND 1,300 billion, belonging to the medium-term public investment plan of the State budget for the period 2021-2025 approved by the Prime Minister.
By early 2025, the Ministry of Transport approved adjusting the total investment of the Dau Giay - Tan Phu expressway project down to more than VND 8,490 billion.
This capital is reduced by nearly 500 billion VND compared to the previous plan. Of which, capital mobilized by investors accounts for more than 7,190 billion VND, state-supported capital accounts for 1,300 billion VND. The payback period is also significantly shortened, from 18 years and 2 months to 16 years and 11 months.
The scale of the project remains the same as before, phase 1 will be built to class 100 highway standards, with a scale of 4 lanes and a roadbed width of 17m. The weak ground sections, bridges and emergency stops will be constructed to a complete scale, with a roadbed width of 24.75m.
When completed, the expressway will reach a design speed of 100km/h, with a scale of 4 lanes and a roadbed width of 24.7m.
The project is invested to meet transportation needs, reduce load and ensure traffic safety on National Highway 20, contribute to the synchronous exploitation of high-capacity, high-speed expressways on the Ho Chi Minh City - Dau Giay - Lien Khuong transport corridor, promote socio-economic development of Dong Nai province and the Southeast region.
Project implementation time from 2024, basically completed in 2026, put into operation from 2027.
Source: https://www.baogiaothong.vn/thuc-tien-do-lua-chon-nha-dau-tu-cao-toc-dau-giay-tan-phu-192250314212128853.htm