Through the campaign "Hand over land first, receive compensation later", the site clearance work for the construction of Dong Dang - Tra Linh expressway through Trang Dinh district, Lang Son province recorded many positive signals.
Recently (November 8), the District Party Committee, People's Council, and People's Committee of Trang Dinh district held a conference to review the peak emulation period and the campaign "Hand over land first, receive compensation later" in the site clearance work for the construction of the Dong Dang - Tra Linh expressway project.
According to the design plan, the project section through Trang Dinh has a total length of more than 27km, uses nearly 195 hectares of land and affects 886 households in 5 communes.
Up to now, the locality has measured and counted 100% of the land area to be recovered, paid 50% compensation in advance with a total amount of more than 41 billion VND for 365 households, successfully mobilized 882/886 households to hand over the land, reaching more than 99.5% of the route length, basically completing the plan assigned by the province.
Mr. Hoang Anh Dung, Deputy Secretary of the District Party Committee, Deputy Head of the Steering Committee for Land Acquisition and Compensation in Trang Dinh District, said that to ensure the progress of site handover, the Steering Committee has assigned tasks to each group to propagate and mobilize each household that is still concerned about issues related to compensation prices and support policies.
"With the motto "close to the people", the district has organized 63 propaganda sessions to help people understand the benefits of the project and agree to hand over the construction site," said Mr. Dung.
It is known that recently, Lang Son province also launched the "High-point Emulation" movement from October to the end of 2024 to speed up the site clearance progress, serving the construction of two expressway projects Dong Dang - Tra Linh and Huu Nghi - Chi Lang.
The Dong Dang - Tra Linh expressway project has a total length of 121km, a total investment of nearly 23,000 billion VND, implemented under the public-private partnership method with Deo Ca Group as the leading investor of the joint venture.
The project is divided into 2 investment phases. In phase 1, the expressway is invested with a length of more than 93km, investment capital of more than 14,300 billion VND, expected to be completed in 2026.
The route starts at the Tan Thanh border gate intersection, Van Lang district, Lang Son province. The end point is at the National Highway 3 intersection in Chi Thao commune, Quang Hoa district, Cao Bang province.
With the drastic participation of the locality in site clearance work, throughout the project site, contractors mobilized more than 1,000 personnel and 350 machines and equipment to deploy on 26 construction sites, the implementation value reached nearly 4% of the contract value.
Source: https://www.baogiaothong.vn/nhieu-ket-qua-tich-cuc-trong-gpmb-thi-cong-cao-toc-lon-qua-lang-son-192241109145021922.htm