After nearly a year and a half of construction, the North-South expressway project in the east through Ha Tinh province with a total length of 102.38 km has taken shape, with some sections already starting to be paved with concrete.
The North-South Eastern Expressway Project, Phase 2021-2025, through Ha Tinh province has a total length of 102.38 km, with 3 component projects: Bai Vot - Ham Nghi, Ham Nghi - Vung Ang and Vung Ang - Bung. The project started on January 1, 2023 and is expected to be completed by the end of 2025.
PHAM DUC
Up to now, after nearly a year and a half of construction, contractors are completing the roadbed, treating weak soil and completing bridge and culvert items on the route.
PHAM DUC
At the Bai Vot - Ham Nghi expressway component project (over 35 km long, total investment of over 7,640 billion VND), passing through Duc Tho, Can Loc, and Thach Ha districts, invested by the Thang Long Project Management Board (Ministry of Transport), contractors are still rushing to complete the construction of roadbeds and bridges and culverts on the route.
PHAM DUC
This expressway section has its starting point at the QL8 intersection in Thanh Binh Thinh commune (Duc Tho district) connecting with the Dien Chau - Bai Vot section, the end point is in Thach Xuan commune (Thach Ha district) connecting with the Ham Nghi - Vung Ang component project.
PHAM DUC
Up to now, the construction has been ensured according to plan, in which the roadbed excavation has reached 60.66%, the weak soil treatment has reached 97.97%; 24/25 bridges on the route are under construction.
PHAM DUC
The Ham Nghi - Vung Ang section (54.2 km long, total investment of VND 9,734.62 billion), passing through Thach Ha, Cam Xuyen and Ky Anh districts, is invested by the Thang Long Project Management Board (Ministry of Transport). The expressway section is divided into 2 construction packages (11-XL and 12-XL) constructed by 6 contractors, of which the private construction enterprise Xuan Truong undertakes the construction of 2/3 of the section.
PHAM DUC
This expressway section has its starting point at Thach Xuan commune (Thach Ha district), connecting with the Bai Vot - Ham Nghi component project and its end point at the QL12C intersection area (in Ky Tan commune, Ky Anh district), connecting with the Vung Ang - Bung component project.
PHAM DUC
After nearly a year and a half of construction, this component project has the fastest construction progress compared to the other two component expressway projects through Ha Tinh province, when the private construction enterprise Xuan Truong has deployed the first asphalt concrete sections.
PHAM DUC
The 55.34 km long Vung Ang - Bung Expressway component project passes through the territory of Ha Tinh (12.9 km) and Quang Binh (42.44 km) provinces with a total investment of more than 12,500 billion VND, invested by Project Management Board 6 (Ministry of Transport).
PHAM DUC
On this route, the Deo But road tunnel is one of the highlights of the expressway through Ha Tinh province. The tunnel is nearly 1 km long, passing through Dong Nang mountain, the north belongs to Ky Lac commune (Ky Anh district), the south belongs to Ky Hoa commune (Ky Anh town). The project is designed permanently, reinforced concrete shell, scale of 2 separate tunnels, each tunnel is 15 m wide, 8 m high.
PHAM DUC
In July 2023, Son Hai Group started drilling the first drill bit to construct the Deo But tunnel and after 10 months of construction efforts, the right tunnel tube in the North-South direction was drilled and cleared, 840 m long. The left tunnel tube was also drilled for 566 m and only about 150 m remained to clear the entire tunnel.
PHAM DUC
According to Son Hai Group's assessment, Dong Nang mountain has a lot of underground water, weak geological foundation, and loose interspersed rocks and soil. During the construction process, contractors encountered many difficulties and had to make some small adjustments compared to the original design to overcome them.
PHAM DUC
According to plan, the North-South expressway project through Ha Tinh will be completed in December 2025, but the Ministry of Transport and the investor are striving to shorten the project completion time by 4-6 months.
Pham Duc - Thanhnien.vn