Today (September 25), Mr. Vo Tan Duc - Chairman of Dong Nai Provincial People's Committee - said that the locality committed that by October 15, the entire land area of the project will be basically handed over to the construction unit.
To ensure progress, Mr. Duc requested that the Bien Hoa - Vung Tau expressway construction units increase human resources and machinery, and work in "3 shifts" to make up for the delayed progress.
According to the report, Long Thanh district has basically completed site clearance, creating conditions for continuous construction.
In Bien Hoa City, despite some difficulties, site clearance is being accelerated, reaching about 50% so far. It is expected that by early October, the city will hand over over 85% of the approved land area.
The Bien Hoa - Vung Tau Expressway is 53.7km long, divided into 3 component projects, with a total investment of 17,828 billion VND. This is one of the key projects in the Southeast region, aiming to connect traffic between Dong Nai and Ba Ria - Vung Tau.
Dong Nai undertakes 2 component projects with a total length of 34.2 km, component project 3 is located in Ba Ria - Vung Tau province.
Dong Nai wants to 'turn' 100-year-old villa into riverside tourist destination
Dong Nai grants investment decisions to 17 projects, total capital of over 155,000 billion VND
Prime Minister Pham Minh Chinh: Dong Nai needs to promote '3 pioneers'
Source: https://vietnamnet.vn/dong-nai-chot-thoi-gian-ban-giao-mat-bang-cao-toc-bien-hoa-vung-tau-2325822.html
Comment (0)