According to the review, in Ha Tinh city, there are currently 3 investment projects using land that are facing many problems.
1. Urban area on both sides of Ngo Quyen Street (Thach Trung Commune)
The project was approved by the Provincial People's Committee under Decision No. 09/QD-UBND dated April 6, 2022 approving Kosy Joint Stock Company as the investor. The project has a total investment capital of VND 796,176 billion, an area of 42.39 hectares in Thach Trung commune.
The Urban Area Project on both sides of Ngo Quyen Street has not completed compensation and site clearance.
According to the plan, phase 1 (from February to November 2022): the investor will complete legal procedures and documents related to the project; site clearance, complete land lease procedures. Phase 2 (from December 2022 to January 2026): invest in the construction of technical infrastructure, townhouses, villas, commercial housing, commercial service areas and other items according to the approved planning; complete procedures for granting land use rights to customers, finalize the project, and hand over administrative management of the project to the People's Committee of Ha Tinh city.
However, up to now, the project has been behind schedule (phase 1), and compensation and site clearance have not been completed.
2. Nam Cau Phu commercial service urban area, ecological villa (Thach Binh commune)
The project was approved by the Provincial People's Committee under Decision No. 1697/QD-UBND dated June 5, 2020, selecting T&T Group Joint Stock Company as the investor with a capital of about VND 3,687.3 billion (excluding compensation and site clearance costs). The project is implemented in Thach Binh commune with an area of 49.91 hectares (the approved planning scale is 71.5 hectares). The project implementation progress is within 30 months from the effective date of the contract.
Perspective of Nam Cau Phu Urban Area, Commercial Services and Ecological Villas
The urban area includes types of housing such as: townhouses, villas, high-rise apartments and social housing; technical infrastructure, traffic systems, public works and green tree systems, water surfaces...
Currently, the approved detailed planning of the project is not consistent with the general planning of the city and Thach Binh commune does not have an approved zoning plan. The entire land area has not yet completed the work of site clearance compensation and local adjustment.
3. Thach Quy urban area (Thach Quy ward)
The project was approved by the Provincial People's Committee under Decision No. 11/QD-UBND dated March 19, 2023, allowing Skyland-Group Investment Joint Stock Company to be the investor. The total capital of the project is VND 278,525 billion, with an investment area of 10.18 hectares. According to the approval decision, the project will be completed and put into operation after 36 months from the date of land allocation and land lease.
Thach Quy urban area project.
After nearly 8 months, up to now, the investor has not had a plan for resettlement infrastructure for households whose land is affected by the project.
Tue Anh
Source
Comment (0)