Blowing the whistle on 7 contractors at a national key project

TPO - Violating the construction contract schedule due to delays in mobilizing personnel, motorbikes, equipment, and materials for construction work, leading to delays, 7 contractors at 2 key national projects were reviewed and criticized.

Báo Tiền PhongBáo Tiền Phong25/03/2025

On March 25, the Dong Nai Province Traffic Construction Investment Project Management Board issued documents notifying the progress of construction contracts and reviewing the construction progress of 7 contractors for Component Project 1, Bien Hoa - Vung Tau Expressway Project and Component Project 3, Ring Road 3 - Ho Chi Minh City Project.

Blowing the whistle on 7 contractors at a national key project photo 1

A section of the Bien Hoa - Vung Tau expressway through Dong Nai province is under construction.

Accordingly, 3 contractors violated the construction contract progress of construction packages at Component Project 1, Bien Hoa Vung Tau Expressway Project including: 479 Hoa Binh Joint Stock Company (construction package No. 18); Construction Corporation No. 1-CTCP (construction package No. 21); Hai Dang Joint Stock Company (construction package No. 21).

In Component Project 3, Ring Road 3 Project - Ho Chi Minh City, there is 1 contractor, Tan Nam Construction Joint Stock Company, which was notified of violating the construction contract progress (package number 26).

Contractors were notified of contract progress violations and criticized for delays in mobilizing personnel, vehicles, equipment, and materials for construction work, leading to delays in construction progress at the site.

The Dong Nai Province Traffic Construction Investment Project Management Board also reviewed and reminded the construction progress of the 3 contractors of Component Project 1, Bien Hoa - Vung Tau Expressway Project, including Truong Son Construction Corporation (member of the consortium implementing package No. 18), Construction Service and Trade Joint Stock Company 68 (implementing package No. 18) and Trung Nam Construction and Installation Joint Stock Company (implementing package No. 18).

The Dong Nai Province Traffic Construction Investment Project Management Board also requested contractors to urgently mobilize human resources and machinery to speed up construction progress on the handed-over area to ensure the completion of the projects.

Source: https://tienphong.vn/tuyt-coi-7-nha-thau-tai-du-an-trong-diem-quoc-gia-post1728090.tpo


Comment (0)

No data
No data

Same category

Overview of the Opening Ceremony of National Tourism Year 2025: Hue - Ancient Capital, New Opportunities
Helicopter squadron carrying the national flag flies over the Independence Palace
Concert Brother Overcomes a Thousand Difficulties: 'Breaking Through the Roof, Flying to the Ceiling, and Breaking Through the Heavens and Earth'
Artists are busy practicing for the concert "The Brother Overcame a Thousand Thorns"

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product