Deputy Minister Nguyen Viet Hung: Focus on accelerating the progress of Hoai Nhon Expressway

Báo Giao thôngBáo Giao thông11/03/2025

On the morning of March 11, Deputy Minister of Construction Nguyen Viet Hung inspected the Hoai Nhon - Quy Nhon Expressway Project.


The amount of work remaining is huge.

At Km 21, Package 11-XL, Hoai Nhon - Quy Nhon Expressway Project, a representative of Truong Son Construction Corporation said that the section through the natural forest from Km 18+650 - Km 21+100 is the project's critical path, and implementation is facing difficulties.

Here, the volume of excavated soil and rock (total remaining excavated volume is about 1.7 million m3) and utilized for roadbed construction and crushed stone production is still very large (about 0.65 million m3), while there are only about 7 months left to complete.

Thứ trưởng Nguyễn Việt Hùng: Tập trung tối đa đẩy tiến độ cao tốc Hoài Nhơn - Quy Nhơn- Ảnh 1.

Deputy Minister Nguyen Viet Hung (dark blue shirt, standing in the middle) listens to a progress report on the Hoai Nhon - Quy Nhon expressway project.

The reason is that the section of the route through the natural forest has been handed over by the locality to both exploit the forest wood and carry out excavation of soil and rocks and mining and crushing rocks to make crushed stone mix from November 30, 2024. However, the handover time is in the middle of the rainy season, so the contractor cannot arrange the construction as planned.

At this section, the contractor is focusing on 6 construction teams to handle the volume of 1.7 million m3 of earth and rock at this section, promptly compensating for the progress.

Deputy Minister Nguyen Viet Hung assessed that this is the most important part affecting the progress of the package and the entire project. The Deputy Minister encouraged the contractor to try to overcome difficulties, and at the same time requested Truong Son Construction Corporation to focus on the construction at the site.

"The contractor needs to focus fully, otherwise the project will not be able to finish. It is necessary to increase machinery and equipment, increase construction sites. Construction must be carried out in 3 shifts, 4 teams, through the sun and rain as the Prime Minister's consistent direction to complete the project," the Deputy Minister requested.

Thứ trưởng Nguyễn Việt Hùng: Tập trung tối đa đẩy tiến độ cao tốc Hoài Nhơn - Quy Nhơn- Ảnh 2.

The Deputy Minister requested Truong Son Construction Corporation to focus fully on accelerating the project's progress.

According to the Deputy Minister, contractors and investors of expressways are currently receiving support, encouragement and close guidance from the Government. The working group led by Deputy Prime Ministers inspected all projects and promptly removed difficulties and obstacles.

Urgently increase machinery and human resources to compensate for slow progress due to weather

Reporting to the Deputy Minister, Project Management Board 85 said that up to now, the construction volume of some main items of the project has been completed, such as roadbed excavation reaching more than 76%; K95 embankment reaching nearly 95%; K98 roadbed embankment reaching more than 69%; grade 1 crushed stone mix reaching more than 59%; reinforced crushed stone mix reaching more than 57%; C19 asphalt concrete reaching more than 19%...

Cumulative output to date is over 5,000 billion VND, reaching over 66% of the contract, 0.22% faster than the approved schedule. Of which, the new 11-XL package has reached about over 1,480 billion/ over 2,691 billion, equivalent to over 55%, 3.73% slower than planned.

Package 12-XL reached approximately 3,556 billion/4,940 billion, equivalent to 72%, meeting the approved adjusted construction schedule. Up to now, the package has basically completed the bridge, culvert, and underpass works on the route.

Thứ trưởng Nguyễn Việt Hùng: Tập trung tối đa đẩy tiến độ cao tốc Hoài Nhơn - Quy Nhơn- Ảnh 3.

The section through natural forest in package 11-XL of Hoai Nhon - Quy Nhon expressway slows down the project's progress.

However, despite efforts to implement the construction, some contractors have not yet met the project's requirements. Among them, Truong Thinh Group Corporation and Urban and Industrial Park Development Investment Corporation (UDIDECO), the total volume of roadbed earthwork of the two units is still relatively large (each contractor has about 90,000 m3), and they need to take advantage of the weather to complete the roadbed work before March 31, 2025 to ensure the progress of the package and the overall progress of the project.

To speed up the progress, Project Management Board 85 requested Truong Son Construction Corporation (contractor of package 11-XL) to increase construction teams, add equipment and human resources, work overtime, and increase shifts to compensate for the delayed progress.

For package 12-XL, contractors also need to increase equipment and machinery, take advantage of the weather that is almost over the rainy season to speed up the earthworks of K95 and K98, ensuring the completion of the earthworks of the main route before March 31, 2025.

The Hoai Nhon - Quy Nhon Expressway has a total length of 70.1km, passing through Binh Dinh province. Total investment: 12,401 billion VND. The investor is Project Management Board 85. The project started on January 1, 2023, the completion date according to the adjusted schedule is September 30, 2025.



Source: https://www.baogiaothong.vn/thu-truong-nguyen-viet-hung-tap-trung-toi-da-day-tien-do-cao-toc-hoai-nhon-quy-nhon-192250311081552311.htm

Comment (0)

No data
No data

Same tag

Same category

Welcoming the sunshine in Duong Lam ancient village
Vietnamese artists and inspiration for products promoting tourism culture
The journey of marine products
Explore Lo Go - Xa Mat National Park

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product