Vice Chairman of the Provincial People's Committee Nguyen Hong Hai has just chaired a meeting to listen to a report on the progress of the site clearance sub-project under the Project to Improve and Upgrade National Highway 28B through Binh Thuan Province. Attending the meeting were leaders of relevant departments, agencies, sectors and localities.
According to the report, from May 13 to 17, 2024, the District People's Committee issued 5 land recovery plans in 5 localities; issued 478 land recovery notices to 475 households, individuals and 3 organizations. From May 20 to June 7, 2024, 406 cases/478 land recovery notices were inventoried (Luong Son 105; Song Luy 27; Song Binh 169; Phan Son 38; Phan Lam 67), reaching a rate of 84.9%. The number of uninvented cases was 72 cases/478 land recovery notices, reaching a rate of 15.1%, mainly due to households and individuals in other localities; buying and selling, transferring through many users; small recovered land area; households and individuals have not agreed to expand the radius of the curves of branch roads connecting to the main road. Currently, the District Land Fund Development Center has transferred the inventory records to localities to consider the legality of the origin, time of land use and ownership of assets on the land; the Department of Natural Resources and Environment is carrying out the procedures for hiring a consulting unit to build specific land prices to carry out compensation and site clearance work.
The District People's Committee has approved the survey task, established the design of the construction estimate and selected a contractor to survey and design the technical infrastructure relocation items of the National Highway 28B Upgrade Project through Binh Thuan Province. Currently, the design contractor has completed the draft design for the relocation of the water supply system and is drafting the design for the relocation of electricity, lighting, and telecommunications.
After listening to the opinions of the delegates attending the meeting, Vice Chairman of the Provincial People's Committee Nguyen Hong Hai said that the Project to Improve and Upgrade National Highway 28B through Binh Thuan and Lam Dong provinces has received great attention from the provincial leaders and is considered one of the important projects of the province. However, due to the deviation of the project's construction drawing design documents compared to the route documents, Project Management Board 5 under the Vietnam Road Administration has not yet handed over the site clearance markers to the locality. Therefore, the Vice Chairman of the Provincial People's Committee requested that Project Management Board 5 further enhance its responsibility in implementing this project. During the implementation process, it is necessary to proactively coordinate with the People's Committee of Bac Binh district to select locations for relocating technical infrastructure works of electricity, water, and telecommunications in the project area. At the same time, it is necessary to be proactive in surveying to promptly hand over the markers to the People's Committee of Bac Binh district to have a basis for carrying out site clearance work; Coordinate with the Department of Agriculture and Rural Development to complete procedures related to the forest land area in this project...
It is known that the Project to Improve and Upgrade National Highway 28B through Binh Thuan and Lam Dong provinces has a total route length of about 69 km, of which the section through Binh Thuan province is about 51 km long; the section through Lam Dong province is about 17 km long. After completion, the project will minimize the risk of traffic accidents on the route, gradually completing the transportation system in Binh Thuan and Lam Dong provinces according to the plan. Thereby, meeting the transportation needs on the East-West corridor, supporting socio-economic development, inter-regional tourism, contributing to poverty reduction and sustainable development for the locality.
Mr. VAN