The contractor has installed guardrails on the Hoai Nhon - Quy Nhon expressway through Binh Dinh province, marking a remarkable progress milestone for this project.
The Hoai Nhon - Quy Nhon Expressway has a total route length of 70.1km through Binh Dinh province, with a total investment of more than VND 12,401 billion, and the investor is Project Management Board 85 (Ministry of Transport). The project started on January 1, 2023 and is expected to be completed by the end of 2025.
In mid-January, at package 12XL of this project, Son Hai Group installed guardrails on the route. Marking an important step in the project's progress.
In mid-January, the construction site was bustling with activity. Son Hai Group divided into 3 construction teams to install guardrails, each team had 3-10 people.
The team of 3 people in front is responsible for driving the guardrail posts. Each guardrail post is 2m apart. This job requires a very high level of precision, even if there is a 1cm deviation, the guardrail panels cannot be mounted because the distances between the holes for mounting the guardrail screws have been designed with pre-set dimensions.
Two workers set the piles in place, one person operates the excavator with a hammer head to fix the piles, ensuring sufficient depth.
The remaining teams with 5-10 workers behind will take on the task of installing the guardrail panels onto the poles that have been fixed by the previous team. Then, attach screws to join the guardrail panels together and fix them to the poles. The work is assigned rhythmically and effectively.
Flexible guardrails used on highway projects are corrugated iron guardrails.
According to Son Hai Group, this type of guardrail was imported from China. Currently, in the 22km that the unit is undertaking the construction of the 12XL Hoai Nhon - Quy Nhon expressway, the unit has installed guardrails for 3km. This unit is also carrying out the second layer of asphalt paving in many sections, striving to complete its part of the work as soon as possible, ahead of schedule.
Project Management Board 85, cumulative output to date at Hoai Nhon - Quy Nhon project has reached more than 4,581 billion VND, reaching 60.03% of the contract, 0.03% faster than the approved schedule.
Video of installing guardrails on Hoai Nhon - Quy Nhon highway:
Source: https://www.baogiaothong.vn/lap-ho-lan-tren-cao-toc-hoai-nhon-quy-nhon-192250117164222101.htm