After just one day and night of historic storm No. 3, the power grid in Quang Ninh province suffered unprecedented damage and chaos. The Electricity Industry is mobilizing all resources to gradually restore the system to soon restore power to customers as soon as possible, with special priority given to key loads such as hospitals, coal mines, water supply plants, etc.

In response to the urgent need to restore power to customers, in Quang Ninh, more than 1,000 people are currently working hard in the rainy and windy weather to restore the province's power grid. Of these, 600 employees are from Quang Ninh Power Company and 450 employees from 8 other provincial power companies (Nghe An, Thanh Hoa, Vinh Phuc, Phu Tho, Ha Tinh, etc.), the Northern Power Service Company, the Northern Power Testing Company (ETC) and contractors.
Today (September 10), the Northern Power Company will continue to mobilize 2 more power companies in other provinces and cities to support Quang Ninh Power Company.
With continuous efforts, as of 8:00 a.m. today, Quang Ninh Electricity Company has restored 22/59 110kV lines (including 5 backup lines); restored 82/180 medium voltage lines; and restored power to over 134,000 customers.

For priority loads in Ha Long City, Quang Ninh Power Company is trying to restore power supply today. The remaining power lines in the city, due to many broken poles, will strive to be repaired in the next few days to restore power supply to customers.
As for the 4 pumping stations for flood control in Dong Trieu town (Thuy An, Hong Phong, Duc Chinh, Viet Dan), there is currently no electricity because the 474E5.23 line has broken and tilted about 30 pole positions. Quang Ninh Electricity Company is trying to fix it in the next few days.