Kinhtedothi - Hanoi strives to complete Component Project 2.1 of the Investment Project to build Ring Road 4 - Capital Region in Hanoi in October 2025.
On March 18, the Office of the Hanoi People's Committee issued Notice No. 131/TB-VP on the conclusions and directions of Chairman of the Hanoi People's Committee Tran Sy Thanh at the meeting to listen to reports on the progress and implementation of the Investment Project to build Ring Road 4 - Capital Region in Hanoi.
Accordingly, after listening to the report of the City Traffic Construction Investment Project Management Board, the opinions of the City Departments, branches and units attending the meeting, the opinions of the Vice Chairmen of the City People's Committee: Duong Duc Tuan, Nguyen Trong Dong, Chairman of the City People's Committee Tran Sy Thanh concluded and directed as follows:
Regarding site clearance: agreeing with the site clearance progress as directed by the Vice Chairmen of the City People's Committee: Duong Duc Tuan and Nguyen Trong Dong in Notice No. 124/TB-VP dated March 13, 2025 of the City People's Committee Office, requesting the People's Committees of districts to continue to focus on implementation, thoroughly resolve the remaining land area to be recovered, and complete before April 15, 2025, this is the final deadline, no later than that.
For Me Linh district: Me Linh district People's Committee continues to focus on implementing site clearance work in the area to ensure completion according to the above schedule; in case households have petitions that are contrary to regulations, violate site clearance policies, intentionally cause complications or oppose, affecting the progress of the Investment Project, consider applying administrative enforcement measures to recover land to ensure progress.
Assign the Director of the Department of Agriculture and Environment to continue working directly and guiding the People's Committee of Me Linh district to remove difficulties and obstacles arising during the implementation process; Assign the Vice Chairmen of the City People's Committee: Duong Duc Tuan and Nguyen Trong Dong to continue directing and thoroughly resolving difficulties and obstacles in Me Linh area.
Regarding the implementation of construction investment component projects: for Component Project 2.1: The City Traffic Construction Investment Project Management Board urges contractors to complete Component Project 2.1 in October 2025 to welcome the City Party Congress.
For Component Project 3: The City Traffic Construction Investment Project Management Board urgently prepares relevant documents so that after selecting an investor, it can immediately resolve the necessary procedures, ensuring the construction progress on May 19, 2025. Relevant City Departments and branches, based on their assigned functions and tasks, proactively coordinate and promptly resolve procedures to ensure the construction progress of Component Project 3.
The City People's Committee assigned the Department of Finance to urgently advise and report to the City People's Committee to transfer the 2024 planned capital source allocated to the Investment Project to ensure funding for payment of the implemented volume of the Investment Project.
Regarding the content of adjusting the total investment: at the meeting of the Steering Committee for important national transport works and projects chaired by the Prime Minister on March 9, 2025, the Prime Minister agreed with the proposal that when the adjusted value of the total investment of the component projects does not exceed the total overall investment, the Hanoi People's Committee is the presiding agency with a unified opinion for the People's Committees of the provinces to decide to approve the adjustment of the Component Project; The City People's Committee has issued a document agreeing for the People's Committee of Bac Ninh province to approve the adjustment of Component Project 1.3; The Department of Finance is assigned to advise and propose a report to the City People's Committee to have a unified document for the People's Committee of Hung Yen province to approve the adjustment of Component Project 1.2.
Source: https://kinhtedothi.vn/du-an-duong-vanh-dai-4-tren-dia-ban-ha-noi-phan-dau-ve-dich-dung-hen.html