On the morning of March 8, Supervisory Delegation No. 4 of the 15th National Assembly, led by Comrade Le Quang Huy - Member of the Party Central Committee, Member of the National Assembly Standing Committee, Chairman of the Science and Technology Committee, conducted a survey on the implementation of Component Project 3 of the Khanh Hoa - Buon Ma Thuot Expressway Project, Phase 1.
Accompanying the delegation were Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee Pham Ngoc Nghi; representatives of relevant departments, branches, units and investors of Component Project 3.
The monitoring delegation listened to a report on the implementation status of Component Project 3 of the Khanh Hoa - Buon Ma Thuot Expressway Project, Phase 1.
Reporting to the working delegation, Deputy Director in charge of the Provincial Traffic Construction and Rural Development Project Management Board Phan Xuan Bach - investor of Component Project 3 said that Component Project 3 has a total length of 48.09 km, passing through 3 districts of Ea Kar, Krong Pac and Cu Kuin; total investment of more than 6,165 billion VND. On the route, 5 different-level interchanges, 28 bridge works and 24 reinforced concrete underpasses are planned.
To date, the project has handed over nearly 46 km of land (reaching 95.41%). Regarding construction, the project is divided into 3 packages, currently the contractors have mobilized hundreds of officers, engineers, workers and hundreds of machines and equipment to construct the project items.
However, during the project implementation, there are still some problems and difficulties such as: according to the provisions of Point d, Clause 3, Article 62 of the 2013 Land Law and the guidance of relevant ministries and branches, the implementation of site clearance at construction material mines is usually carried out according to the agreement mechanism between the contractor and the land user. However, in reality, the work of negotiating compensation and support for land for exploiting material mines encounters many difficulties. In addition, there is currently no guidance on determining the price of materials at the mine granted according to a specific mechanism including transfer price, land use right lease, crop compensation, etc.
Units are implementing the construction of Component Project 3 section through Krong Pac district.
To resolve the above difficulties, Dak Lak province recommends that the Monitoring Team consider and request the Government and relevant ministries and branches to provide guidance on determining the price of materials at the mine; recommends that the Government consider and submit to the National Assembly a resolution allowing localities to carry out land recovery, prepare and approve compensation plans, and clear the site according to the procedures prescribed by the land law for common construction material mines serving national key projects; promptly issue instructions on implementing a specific mechanism for exploiting minerals for common construction materials to supply to the project...
After surveying the Project, Comrade Le Quang Huy - Member of the Party Central Committee, Member of the National Assembly Standing Committee, Chairman of the Science and Technology Committee acknowledged and highly appreciated the drastic participation of the Dak Lak province's political system in the implementation of site clearance and project implementation. Regarding the province's recommendations, the Delegation acknowledged and will synthesize and submit to the National Assembly and send to the Government, ministries and branches for consideration and solutions to speed up the implementation of Component Project 3 of the Khanh Hoa - Buon Ma Thuot Expressway Project Phase 1.