Vietnam.vn - Nền tảng quảng bá Việt Nam

Continue to spend tens of billions of dong to restore Hue Citadel

HUE - The project to preserve, restore and embellish the Hue Citadel system with a total cost of nearly 50 billion VND is being implemented.

Báo Lao ĐộngBáo Lao Động09/04/2025


In June 2023, Area 1 of the Upper Citadel and Eo Bau (one side to the South and one side to the East of Hue Citadel) was renovated, abandoned houses were leveled and trees and grass were cleared. This is a project accompanying the resettlement work in the Upper Citadel, invested by the Hue City Land Fund Development Center, with a total cost of more than 35 billion VND. (Photo taken in December 2024, the Eo Bau part to the East of the Citadel was renovated).

In June 2023, Area 1 of the Upper Citadel and Eo Bau (one side to the South and one side to the East of Hue Citadel) was renovated, abandoned houses were leveled and trees and grass were cleared. This is a project accompanying the resettlement work in the Upper Citadel, invested by the Hue City Land Fund Development Center, with a total cost of more than 35 billion VND. (Photo taken in December 2024, the Eo Bau part to the East of the Citadel was renovated).

In early 2025, Hue City will continue to implement the Project to Preserve, Restore and Renovate the Hue Citadel System, including the items of restoration and renovation of the Upper Citadel, Eo Bau and the stone embankment of the Ho Thanh moat from Quan Tuong Dai to Tay Thanh Thuy Quan (the project area is being implemented).

In early 2025, Hue City will continue to implement the Project to Preserve, Restore and Renovate the Hue Citadel System, including the items of restoration and renovation of the Upper Citadel, Eo Bau and the stone embankment of the Ho Thanh moat from Quan Tuong Dai to Tay Thanh Thuy Quan (the project area is being implemented).

The project, invested by the Hue Monuments Conservation Center with a total budget of VND49.3 billion, aims to protect and maintain heritage values, reinforce degraded structures, and improve the landscape of the area.

The project, invested by the Hue Monuments Conservation Center with a total budget of VND49.3 billion, aims to protect and maintain heritage values, reinforce degraded structures, and improve the landscape of the area.

The project will renovate the Upper Citadel, covering an area of ​​892m2 and 21m wide. It includes excavation, earthworks, and paving of Bat Trang bricks for walkways and artillery platforms.

The project will renovate the Upper Citadel, covering an area of ​​892m2 and 21m wide. It includes excavation, earthworks, and paving of Bat Trang bricks for walkways and artillery platforms.

The remaining land area will be covered with clover and damaged and cracked walls will be reinforced to ensure structural stability.

The remaining land area will be covered with clover and damaged and cracked walls will be reinforced to ensure structural stability.

The Tay An and Tay Trinh Passes, located within the Hue Citadel, will also be renovated. This includes earthworks, rebuilding artillery ramps, reinforcing retaining walls with boulders, restoring ammunition depots, and paving walkways with Bat Trang tiles. (The area around the ammunition depot will be renovated.)

The Tay An and Tay Trinh Passes, located within the Hue Citadel, will also be renovated. This includes earthworks, rebuilding artillery ramps, reinforcing retaining walls with boulders, restoring ammunition depots, and paving walkways with Bat Trang tiles. (The area around the ammunition depot will be renovated.)

With the Ho Thanh moat system, the focus will be on repairing and embellishing the 1,159m long inner stone embankment, stretching from Quan Tuong Dai to Tay Thanh Thuy Quan. Damaged and eroded embankments will be dismantled, cleaned and old materials will be reused during the restoration process.

With the Ho Thanh moat system, the focus will be on repairing and embellishing the 1,159m long inner stone embankment, stretching from Quan Tuong Dai to Tay Thanh Thuy Quan. Damaged and eroded embankments will be dismantled, cleaned and old materials will be reused during the restoration process.

The foundation of the embankment will be reinforced by driving bamboo piles, pouring reinforced concrete and rebuilding with rubble combined with cement mortar. In addition, the trench will also be dredged of mud, built with a cofferdam and treated for diversion.

The foundation of the embankment will be reinforced by driving bamboo piles, pouring reinforced concrete and rebuilding with rubble combined with cement mortar. In addition, the trench will also be dredged of mud, built with a cofferdam and treated for diversion.

The project to preserve, restore and embellish the Hue Citadel system is expected to be completed in October 2027. (The Quan Tuong Dai area of ​​the upper citadel will be renovated and embellished.)

The project to preserve, restore and embellish the Hue Citadel system is expected to be completed in October 2027. (The Quan Tuong Dai area of ​​the upper citadel will be renovated and embellished.)

When completed, the project is expected to change the landscape, restoring the original appearance of the Upper Citadel and Eo Bau relics. In the future, it will be opened to serve the sightseeing needs of residents and tourists.

When completed, the project is expected to change the landscape, restoring the original appearance of the Upper Citadel and Eo Bau relics. In the future, it will be opened to serve the sightseeing needs of residents and tourists.

Source: https://laodong.vn/photo/tiep-tuc-chi-hang-chuc-ti-dong-tu-bo-kinh-thanh-hue-1488147.ldo




Comment (0)

No data
No data

Same tag

Same category

Young people "revive" historical images
Close-up of the soldiers' hard training hours before the April 30th celebration
Ho Chi Minh City: Coffee shops decorated with flags and flowers to celebrate the 30/4 holiday
36 military and police units practice for April 30th parade

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product