The above direction was given by Prime Minister Pham Minh Chinh on the afternoon of January 27, during a working trip to the four provinces of Thai Binh, Nam Dinh, Ninh Binh and Thanh Hoa to inspect the construction and give gifts to encourage the construction forces of the 500kV line 3 circuit project from Quang Trach (Quang Binh province) to Pho Noi (Hung Yen province).
The Prime Minister and the delegation inspected the construction and presented gifts to encourage the construction forces at 4 locations in 4 provinces: Location 201 in Chau Son commune, Quynh Phu district, Thai Binh; Location 13 in Nghia Hong commune, Nghia Hung district, Nam Dinh province; Location 41 in Thuong Kiem commune, Kim Son district, Ninh Binh province; Location 100 in Ha Hai commune, Ha Trung district, Thanh Hoa province.
The Prime Minister encouraged and gave gifts to workers at the construction site of column foundation position 201 (Photo: Doan Bac).
At the inspection locations, the head of the Government assessed the 500kV line 3 extension project as a key, urgent project, playing an important role in national energy security, especially for the Northern region.
The Prime Minister commended the Vietnam Electricity Group, relevant ministries, branches, agencies and localities for their efforts to overcome difficulties, promptly resolve problems as directed, start the project and focus on construction.
He requested ministries, branches and the Electricity Corporation to closely coordinate with local authorities and relevant units to mobilize maximum human and material resources, including on-site forces, on-site means and on-site materials to construct the project.
The Prime Minister emphasized the spirit of responsibility, initiative, and creativity in construction along with the requirements of ensuring quality, technique, progress, savings, labor safety, and environmental sanitation.
"Implement this project with the spirit of only working, not backtracking, working in 3 shifts, 4 teams, overcoming the sun, overcoming the rain, working through holidays and Tet, eating and sleeping urgently", according to the direction of the head of the Government.
The Prime Minister talks with workers constructing site 41 in Thuong Kiem commune, Kim Son district, Ninh Binh province (Photo: Doan Bac).
In addition, the Prime Minister noted that units must proactively respond to unusual external impacts on the construction process such as weather, natural disasters, environment, etc.; promptly remove arising obstacles and be determined to complete and put the project into operation in June.
During the construction process, the Prime Minister reminded units to try to apply modern scientific and technological solutions to speed up progress and improve quality.
For localities, the Government leaders requested to urgently complete the handover of land for the project; ensure security, order and safety in construction at the project area; and compensate appropriately and legally for people who have given up land for the project.
For people who have projects passing through and are affected by the project, the Prime Minister hopes that people will continue to support and actively participate when mobilizing and supporting construction forces; ensuring safety, security and order during the project construction process, for the benefit of the nation, the development of each locality and for the benefit of each individual.
Workers worked through the night to complete the 500kV line passing through 9 provinces (Photo: Doan Bac)
Sharing information at the construction site, Chairman of the Board of Members of Vietnam Electricity Group (EVN) Dang Hoang An said that this is an important and urgent energy project, passing through many localities and must be implemented in a short time.
However, with the strong direction of the Prime Minister and the participation of ministries, branches, localities and the support of the people, up to now, the project has achieved certain results.
"The investor will closely follow the instructions, focus all resources, and closely coordinate with relevant parties to implement work items in parallel and smoothly, ensuring compliance with regulations and striving to achieve the set progress according to the Prime Minister's instructions," said Mr. An.
The 500kV line 3 project from Quang Trach to Pho Noi (500kV line 3 extension) includes 4 component projects; has a total length of about 519km with 1,179 pole foundation locations; total investment of about 22,000 billion VND.
The project passes through 211 communes and wards of 43 districts and towns in 9 provinces: Quang Binh, Ha Tinh, Nghe An, Thanh Hoa, Ninh Binh, Nam Dinh, Thai Binh, Hai Duong, Hung Yen.
Of which, the earliest component project to start construction on October 25, 2023 is the 500kV Nam Dinh I Thermal Power Plant - Thanh Hoa Transmission Line project; the remaining 3 component projects are the 500kV Nam Dinh I Thermal Power Plant - Pho Noi Transmission Line; Quynh Luu - Thanh Hoa and Quang Trach - Quynh Luu Transmission Lines simultaneously started construction on January 18.