Deputy Prime Minister Mai Van Chinh inspects the Ho Chi Minh City Ring Road 3 project

Báo Tiền PhongBáo Tiền Phong11/03/2025

TPO - Today, March 11, Deputy Prime Minister Mai Van Chinh and his working delegation inspected, reviewed, and removed difficulties and obstacles at the Ho Chi Minh City Ring Road 3 construction project.


TPO - Today, March 11, Deputy Prime Minister Mai Van Chinh and his working delegation inspected, reviewed, and removed difficulties and obstacles at the Ho Chi Minh City Ring Road 3 construction project.

Mr. Luong Minh Phuc - Director of the Management Board of Investment and Construction of Traffic Works of Ho Chi Minh City (abbreviated as the Traffic Board, investor of the Ring Road 3 project through Ho Chi Minh City) said that the Ring Road 3 construction project in Ho Chi Minh City has a total length of 76km, passing through four localities including Ho Chi Minh City, Dong Nai, Binh Duong and Long An, with a total investment of 75,378 billion VND.

Deputy Prime Minister Mai Van Chinh inspects the Ho Chi Minh City Ring Road 3 project photo 1

Mr. Luong Minh Phuc - Director of the Ho Chi Minh City Department of Transport (left photo) reports to the Government delegation on the progress of the Ho Chi Minh City Ring Road 3 project. Photo: AX

Reporting on the overall progress of the project, Mr. Phuc said that the output of Long An province reached more than 62%, Ho Chi Minh City reached 31%, Dong Nai reached 25% and Binh Duong province reached 24%.

To strengthen the connection between Ho Chi Minh City and Dong Nai, the Traffic Department is striving to complete the elevated section of Ring Road 3 in Thu Duc City by the end of this year, and the remaining sections will strive to be completed by June 30, 2026.

"The Traffic Department is making efforts to speed up the progress to exploit synchronously with the 1A component project invested by the My Thuan Project Management Board. On this April 30, Ho Chi Minh City will connect with Nhon Trach Bridge, technically open a section of the Ring Road 3 project. By the end of this year, Ring Road 3 will have an additional 14.7km of elevated section in Thu Duc City that will be technically open to traffic" - Mr. Phuc shared.

Deputy Prime Minister Mai Van Chinh inspects the Ho Chi Minh City Ring Road 3 project photo 2

A section of Ho Chi Minh City's Ring Road 3 (elevated section) through Thu Duc City. Photo: HQ

Regarding difficulties, currently in Ho Chi Minh City, there are still problems with land acquisition in Binh Chanh District (1 case) and Thu Duc City (7 cases). It is expected that by the end of March, Ho Chi Minh City will have 100% of land acquisition to speed up construction progress. Regarding difficulties in sand sources for embankment, Mr. Phuc said that this is a common difficulty for all 4 localities where the project passes through. Therefore, the project needs a specific mechanism to increase the exploitation capacity of sand and material mines.

Deputy Prime Minister Mai Van Chinh inspects the Ho Chi Minh City Ring Road 3 project photo 3

Nhon Trach Bridge connects Nhon Trach District (Dong Nai) with Thu Duc City (HCMC). This is a component project of Section 1A - Ho Chi Minh City Ring Road 3.

At the survey on March 11, Deputy Prime Minister Mai Van Chinh acknowledged the efforts of Ho Chi Minh City and localities in implementing the Ring Road 3 project, and difficulties and obstacles will be studied and resolved.

“This is a key project, of great significance, for the development of the regional economy. Therefore, it is necessary to be decisive, mobilize forces, machinery, and maximize human resources. The investor needs to acknowledge the working spirit, focus on determination, and discuss the progress to ensure the quality of the project" - Deputy Prime Minister Mai Van Chinh directed.

According to the My Thuan Project Management Board (investor of component project 1A of Ho Chi Minh City Ring Road 3), the investor and contractor are currently actively speeding up the progress of component project 1A, especially the Nhon Trach bridge. Specifically, the project progress has reached 87.18%, of which the Nhon Trach bridge construction package has reached 94.55% and the approach road construction package has reached 76.13%.

Component 1A plays an important role in shortening the distance from Ho Chi Minh City - Dong Nai to Long Thanh International Airport. This project is expected to be completed by June 30, helping to reduce the load on the Ho Chi Minh City - Long Thanh - Dau Giay Expressway, contributing to remote traffic flow, reducing congestion on expressways as well as the inner-city road system of Ho Chi Minh City.

Currently, the investor and contractors are making efforts and committing to compete to speed up the progress within 60 days to complete the entire Nhon Trach bridge, basically paving the asphalt concrete section of the approach road before April 26 and technically opening the entire 8.22 km route of component project 1A on April 27.

Ho Chi Minh City is about to auction a series of
Ho Chi Minh City is about to auction a series of "golden" lands along the metro and Ring Road 3.

Binh Duong builds nearly 100km of road along Saigon River, parallel to Ho Chi Minh City's Ring Roads 3 and 4.
Binh Duong builds nearly 100km of road along Saigon River, parallel to Ho Chi Minh City's Ring Roads 3 and 4.

Ho Chi Minh City has selected 11 locations for TOD along the metro line and beltway 3.
Ho Chi Minh City has selected 11 locations for TOD along the metro line and beltway 3.

Huynh



Source: https://tienphong.vn/pho-thu-tuong-mai-van-chinh-kiem-tra-du-an-vanh-dai-3-tphcm-post1724046.tpo