The resettlement land location for the Bien Hoa - Vung Tau expressway project has the lowest price of 7.7 million VND/m2, the location with the highest price is 12.7 million VND/m2.
According to news from Dong Nai province, Long Thanh district and Bien Hoa city are currently focusing on compensation, site clearance and determining land prices for the two resettlement areas of Tam Phuoc and Phuoc Tan, which are part of the Bien Hoa - Vung Tau expressway construction investment project.
Currently, Bien Hoa - Vung Tau expressway is in the accelerated construction phase.
According to Mr. Tran Van Than, Vice Chairman of Long Thanh District People's Committee, for component project 1 and component 2 of Bien Hoa - Vung Tau expressway, the section passing through the district has a total length of 28km, the recovered land area is nearly 230ha. Up to now, 84% of the site has been handed over to the investor, and 94% of the site has been handed over for component project 2.
Currently, site clearance is a great pressure for the locality. The reasons are the large number of projects, some new legal regulations have not been applied, compensation prices have not met people's wishes, the provincial compensation council is short of staff...
Therefore, there should be general guidelines for the whole province on compensation work, clearly stating the procedures, cases not yet regulated by law, and other support policies to facilitate local implementation and reduce risks.
The demand for resettlement housing of the people is very high, early resettlement will also help people move early, giving up land for projects.
In Long Thanh district, there are 2 resettlement areas, of which the resettlement area in Long Duc commune has basically completed the infrastructure, some of which have handed over land to people to build houses. The resettlement area in Long Phuoc commune has cleared 99% of the land, and currently the infrastructure construction is 76%.
Similarly, Mr. Vu Quoc Thai, Vice Chairman of Bien Hoa City People's Committee, said that the Component 1 project through the city is 6.2km long, with an area to be recovered of 59.5ha. Up to now, more than 45ha, equivalent to more than 76%, has been handed over. Currently, Bien Hoa is focusing on clearing the area at the beginning of the route, adjacent to Vo Nguyen Giap Street, to have a clean area to ensure construction.
Bien Hoa City plans two resettlement areas in Tam Phuoc and Phuoc Tan wards. The difficulty is that up to now, these resettlement areas have not yet cleared the land, have not yet acquired the land, and have not yet started infrastructure construction.
Regarding the land prices of the two resettlement areas of the Bien Hoa - Vung Tau Expressway in Bien Hoa City, according to the Department of Natural Resources and Environment, there is currently not enough basis to add the land price list of these two resettlement areas to the land price list for the period 2020-2024, lasting until the end of 2025 of the province. This Department proposed a provisional resettlement land price. According to the proposal, the resettlement land location with the lowest price is 7.7 million VND/m2, the location with the highest price is 12.7 million VND/m2.
Regarding these issues, Mr. Ho Van Ha, Vice Chairman of Dong Nai Provincial People's Committee, said that the Bien Hoa - Vung Tau Expressway is in urgent need of progress. The work of site clearance, relocation of technical infrastructure, construction of the expressway, and construction of resettlement areas needs to be more urgent.
Investors, construction units, infrastructure management units, and localities must closely coordinate in carrying out tasks. Strive to complete project site clearance by next March. It is necessary to quickly provide information to people on resettlement land prices, support policies for people directly involved in agricultural production; and housing support policies for cases that do not meet resettlement conditions.