Accordingly, the project is over 621 m long, the roadbed is 18 m wide and 4.5 cm thick, with a total investment of nearly 3 billion VND. The construction unit (Cat Minh Joint Stock Company) has mobilized resources with 4 rollers, 1 paver, 5 cars and 15 workers to focus on construction to ensure the set progress. Along with paving the road surface, the construction unit also implemented other items such as installing traffic signs and painting road markings.
It is known that the pilot period for opening the route starts from March 3 to April 18, 2025 (45 days) and follows 2 time frames: from 6:00 to 8:00 and from 10:30 to 13:30 every day. The types of vehicles allowed to travel on this route are cars with 9 seats or less, rudimentary vehicles, motorbikes, and motorcycles (cars with more than 9 seats, trucks, and animal-drawn vehicles are prohibited); stopping and parking are prohibited in the Square area; the permitted speed is under 40km/h.